Weil-McLain CGS-4E Gas piping, Connecting gas supply piping to boiler, Natural Gas, Propane Gas

Page 25

GOLD CGs-4E Gas-Fired Water Boiler — Boiler Manual

5 Gas piping

Connecting gas supply piping to boiler

1.Remove jacket front panel and refer to Figure 14 to pipe gas to boiler.

a.Install drip leg at inlet of gas connection to boiler. Where local utility requires drip leg to be extended to the floor, use appropri- ate length of pipe between cap and tee.

b.Install ground joint union for servicing, when required.

c.Install manual shutoff valve in gas supply piping outside boiler jacket when required by local codes or utility requirements.

d.In Canada — When using manual main shutoff valve, it must be identified by the installer.

2.Support piping with hangers, not by boiler or its accessories.

3.Purge all air from gas supply piping.

4.Before placing boiler in operation, check boiler and its gas connection for leaks.

a.Close manual main shutoff valve during any pressure testing at less than 13” w.c.

b.Disconnect boiler and gas valve from gas supply piping dur- ing any pressure testing greater than 13” w.c.

Do not check for gas leaks with an open flame — use bubble test. Failure to use bubble test or check for gas leaks can cause severe personal injury, death or substantial property damage.

5.Use pipe dope compatible with propane gases. Apply sparingly only to male threads of pipe joints so that pipe dope does not block gas flow.

Failure to apply pipe dope as detailed above can result in severe personal injury, death or substantial property damage.

Natural Gas:

1.Refer to Table 4 for pipe length and diameter. Base on rated boiler input (divide by 1,000 to obtain cubic

feet per hour). Table 4 is only for gas with specific gravity 0.60, with a pressure drop through the gas piping of 0.30” w.c. For additional gas pipe sizing information, refer to ANSI Z223.1 (or B149.1 or B149.2 for Canadian installations).

2.Inlet pressure required at gas valve inlet:

Maximum: 13” w.c.

Minimum: 5” w.c.

Manifold gas pressure: 3.50” w.c. at high fire (0.90” w.c. at low fire while in low fire at start- up)

3.Install 100% lockup gas pressure regulator in supply line if inlet pressure exceeds 13” w.c. Adjust for 13” w.c. maximum.

Propane Gas:

1.Contact gas supplier to size pipes, tanks and 100% lockup gas pressure regulator.

2.Adjust propane supply regulator provided by gas supplier for 13” w.c. maximum pressure.

3.Inlet pressure required at gas valve inlet:

Maximum: 13” w.c.

Minimum: 11” w.c.

Manifold gas pressure: 10” w.c. at high fire (3.50” w.c. at low fire while in low fire at start- up)

Table 4 

Pipe capacity for 0.60 specific gravity natural gas

 

Figure 14  Gas supply piping

 

 

 

 

 

 

 

 

 

 

Gas

 

 

 

Capacity of pipe for pipe size of:

 

 

pipe

 

 

(Capacity in cubic feet gas per hour)

 

 

length

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(feet)

 

½”

 

¾”

1”

1¼”

 

1½”

 

 

 

 

 

 

 

 

 

 

 

10

 

132

 

278

520

1050

 

1600

 

 

 

 

 

 

 

 

 

 

 

20

 

92

 

190

350

730

 

1100

 

 

 

 

 

 

 

 

 

 

 

30

 

73

 

152

285

590

 

860

 

 

 

 

 

 

 

 

 

 

 

40

 

63

 

130

245

500

 

760

 

 

 

 

 

 

 

 

 

 

 

50

 

56

 

115

215

440

 

670

 

 

 

 

 

 

 

 

 

 

 

75

 

45

 

93

175

360

 

545

 

 

 

 

 

 

 

 

 

 

 

100

 

38

 

79

150

305

 

460

 

 

 

 

 

 

 

 

 

 

 

150

 

31

 

64

120

250

 

380

 

 

 

 

 

 

 

 

 

 

 

Part number 550-110-282/1108

25

Image 25
Contents GOLDCGs-4E How it works Gold CGs-4EGas-Fired Induced-Draft Water Boiler Contents Please read before proceeding InstallerUser Installations must follow these codes 1a Prepare boiler location codes & checklistBefore locating the boiler, check the following 1b Prepare boiler location clearances 1c Prepare boiler location vent system When removing boiler from an existing common vent systemCGs-4E special vent system Vent systemProducts to avoid 1d Prepare boiler location contaminationAreas likely to have contaminants Combustion air requirements 1e Prepare boiler location air openingsSpecial considerations Sizing air openingsSizing air openings for CGs-4E installations Orifice replacement procedure 2a Prepare boiler placement & setupPlace boiler/crate near position Inspect orifices and burnersHydrostatic pressure test 2b Prepare boiler pressure testDrain and remove fittings Prepare boiler for test3a Water piping general information 3b Water piping single-zone system Install an automatic air vent in air vent tapping as shownPiping multiple zones 3c Water piping multiple zonesSystem or zone circulator Zone valve Drain valve Boiler isolation balancing valves Flow/check valveRelief valve Fill valveValve adjustment Figures 8 and 9 only Temperature gauges3d Piping low temp systems Primary/secondary preferred bypass piping methodBoiler isolation balancing valves Blend temperature gaugeBOILER-bypass piping method Valve adjustmentFigures 8 SYSTEM-bypass piping method Prevent chilled water from entering 3e Water piping refrigeration systemsBoiler Vent system Venting and combustion airCombustion air openings Combustion air quality Gas piping Connecting gas supply piping to boilerNatural Gas Propane GasElectrical installation must comply with Field wiringWiring connections Thermostat7a Start-up preparation Freeze protection when usedDetermine if water treatment is needed Check for gas leaksInspect system water piping Inspect base insulation 7b Start-up operate boilerFinal check before starting boiler Start the boilerPilot burner flame Figure Check burner flamesMain burner flame Figure 7c Start-up if boiler doesn’t start If none of the above corrects the problem, refer toCheck for Gas not turned on at meter or boiler?Installation and service certificate Check-out procedure checklistSequence returns to step 9a Operation sequenceBoiler is now in the off cycle Operation sequence Wiring diagram 9b Operation wiring diagrams9c Operating instructions CGs-4E CMR 5.082a 1 through Addendum Instruction for Commonwealth of MassachusettsExemptions The following equipment is exempt from CMR 5.082a1 through10a Service and maintenance schedule 10b Service & maintenance annual start-up Burners, base and inlet air box With boiler power off, place a few drops of S.A.ECondensate drain system Inducer motor10b Service & maint. annual start-up Relief valve, typical Boiler relief valveReview with owner Clean between sections with wire flue brushShut down boiler Place newspapers in base of boiler to collect sootBefore troubleshooting 11a Troubleshooting procedureCheck the following Can resultAir pressure switch 11b Troubleshooting air pressure switchCheck pressure switch setting Troubleshooting air pressure readingControl indicator lights Lockout modes 11c Troubleshooting control moduleControl indicator lights NON-LOCKOUT modes Troubleshooting the control moduleControl module connections Chart 1 Troubleshooting Power light status 11d Troubleshooting control module lightsChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Does blower motor operate? Item 8 , Verify Sequence of operation, , Section assembly Base Jacket Trim Controls 12a Replacement partsWeil-McLain part numbers are found in Weil-McLain Boilers Weil-McLain part number 12b Replacement parts section assemblyBase assembly 12c Replacement parts baseDescription Weil-McLain Part number Jacket assembly 12d Replacement parts jacketBoiler Fittings shown are factory-installed on boiler 12e Replacement parts trimPropane gas components 12f Replacement parts controlsDimensional drawing 13a DimensionsTested for 50 psi working pressure 13b RatingsThis type of respirator is based on Handling ceramic fiber and fiberglass materialsEye Irrigate immediately Breathing Fresh air