Weil-McLain 550-110-260/02002 2b Prepare boiler pressure test, Perform hydrostatic pressure test

Page 13

Boiler Manual

2b Prepare boiler — pressure test

Perform hydrostatic pressure test

Pressure test boiler before attaching water or gas piping (except as noted below) or electrical supply.

Prepare boiler for test

1.Remove the shipping nipple (from CGs supply tapping) and remove the boiler relief valve. Temporarily plug the relief valve tapping with a ¾" NPT pipe plug.

2.Remove 1¼" nipple, reducing tee and drain valve from accessory bag. Install in boiler return connection as shown on page 3 and Figure 29, page 56. Install circulator on either the return or supply.

3.Remove 1¼" nipple, 1¼" tee, bushing and pressure/temperature gauge from accessory bag. Pipe to boiler supply connection as shown on page 3 and Figure 29, page 56. (Use pipe dope sparingly.)

4.Connect a hose to boiler drain valve, the other end connected to a fresh water supply. Make sure hose can also be used to drain boiler after test.

5.Connect a nipple and shutoff valve to system supply connection on the 1¼" tee. This valve will be used to bleed air during the fill. (Valve and nipple are not included with boiler.)

6.Connect a nipple and shutoff valve to system return connection (at circulator flange if circulator installed on return). This valve will be used to bleed air during the fill. (Valve and nipple are not included with boiler.)

Fill and pressure test

1.Open the shutoff valves you installed on supply and return connections.

2.Slowly open boiler drain valve and fresh water supply to fill boiler with water.

3.When water flows from shutoff valves, close boiler drain valve.

4.Close shutoff valves.

5.Slowly reopen boiler drain valve until test pressure on the pressure/temperature gauge reaches no more than:

45 psig for boilers with 30 psig relief valve.

75 psig for boilers with 50 psig relief valve.

6.Test for no more than 10 minutes at:

45 psig for boilers with 30 psig relief valve.

75 psig for boilers with 50 psig relief valve.

Do not leave boiler unattended. A cold water fill could expand and cause excessive pressure, resulting in severe personal injury, death or substantial property damage.

7.Make sure constant gauge pressure has been maintained throughout test. Check for leaks. Repair if found.

Leaks must be repaired at once. Failure to do so can damage boiler, resulting in substantial property damage.

Do not use petroleum-basedcleaning or sealing compounds in boiler system. Severe damage to boiler will occur, resulting in substantial property damage.

Drain and remove fittings

1.Disconnect fill water hose from water source.

2.Drain boiler at drain valve or out hose, whichever provides best access to drain. Remove hose after draining if used to drain boiler.

3.Remove nipples and valves unless they will remain for use in the system piping.

4.Remove plug from relief valve tapping. See section 3a to replace relief valve.

Part number 550-110-260/0200

13

Image 13
Contents Page ① Control module How it worksPage Contents Please read before proceeding InstallerUser 1a Prepare boiler location codes & checklist 1b Prepare boiler location clearances Residential garage installationFlooring and foundation Removing from existing vent 1c Prepare boiler location vent systemAir contamination 1d Prepare boiler location contaminationCGs combustion air options 1e Prepare boiler location air openingsSizing air openings for CGs installations Orifice replacement procedure 2a Prepare boiler placement & setupPlace boiler/crate near position Inspect orifices and burnersPerform hydrostatic pressure test 2b Prepare boiler pressure testPrepare boiler for test Fill and pressure test3a Water piping general information Expansion tank 3b Water piping single-zone systemDiaphragm-type or bladder-type expansion tank Figure Closed-type expansion tank FigureConverted gravity or steam systems 3c Water piping multiple zonesTypical piping multiple-zone installations 3d Water piping low temp systems Temperature gauges Valve adjustmentFor radiant heating or converted gravity systems Primary/secondary preferred bypass piping3e Water piping low temp systems Boiler-bypass alternate piping 3f Water piping low temp systems 3g Water piping refrigeration system 3f system-bypass alternate pipingPrevent chilled water from entering boiler Venting and combustion air Connecting gas supply piping to boilerGas piping Length Natural GasWiring connections Field wiringThermostat Junction Box furnished7a Start-up preparation Freeze protection when usedDetermine if water treatment is needed Check for gas leaks7b Start-up operate boiler 7a Start-up preparationCheck burner flames 7c Start-up if boiler doesn’t startCheck for Installation and service certificate Check-out procedure checklistRaise room thermostat to call for heat 9a Operation sequenceSchematic wiring diagram 9b Operation wiring diagramsService 9c Operation lighting instructions For Your Safety Read Before OperatingService technician 10a Service and maintenance schedule10b Service & maintenance annual start-up Boiler heating surfaces Burners, base and inlet air boxCondensate drain system Inducer motor10b Service & maint. annual start-up Lever must be operated AT Least Boiler relief valveReview with owner Before troubleshooting 11a Troubleshooting procedureCheck pressure switch setting 11b Troubleshooting air pressure switchControl indicator lights lockout modes 11c Troubleshooting control moduleControl module connections Chart 1 Troubleshooting Power light status 11d Troubleshooting control module lightsChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Turn OFF Power to boiler at service switch or breaker Does blower motor operate? Verify Sequence of operation, , 12a Replacement parts Page Page Page Page Page Dimensional drawing 13a DimensionsDOE 13b RatingsRemoval of Combustion Chamber Lining or Base Panels Handling ceramic fiber and fiberglass materials

550-110-260/02002 specifications

Weil-McLain is a well-known manufacturer of high-quality heating systems and boiler solutions, and the 550-110-260/02002 model is a testament to the company's commitment to innovation and performance. This particular boiler is designed for commercial and residential applications, providing exceptional heating efficiency and reliability.

One of the standout features of the Weil-McLain 550-110-260/02002 is its robust construction. Built using durable materials, this boiler is engineered to withstand demanding environments while maintaining optimal performance. The unit boasts a high thermal efficiency rating, which translates to lower energy costs and reduced environmental impact. The advanced design ensures that fuel consumption is minimized while delivering consistent heat output.

The Weil-McLain 550-110-260/02002 utilizes a multi-stage burner that enhances combustion efficiency. This feature not only reduces emissions but also improves overall energy use, making it an environmentally friendly choice. The sophisticated control system allows for precise modulation of the burner, ensuring that the boiler operates at peak efficiency under various load conditions.

The boiler is equipped with a user-friendly digital control interface, providing operators with real-time monitoring and diagnostics. This allows for easy adjustments and troubleshooting, which helps to reduce maintenance downtime. The integrated safety features enhance the operational reliability of the unit, ensuring safe operation in any environment.

Another important characteristic of the Weil-McLain 550-110-260/02002 is its adaptability. It can be configured to work with various types of fuel including natural gas and propane, giving users the flexibility to choose the most cost-effective energy source. This versatility also helps to extend the lifespan of the boiler as it can be easily adapted to changing energy needs.

In conclusion, the Weil-McLain 550-110-260/02002 is a high-performance boiler that combines durability, efficiency, and advanced technology. With its robust construction, efficient burner system, and user-friendly controls, it stands out as a reliable heating solution for both commercial and residential applications. The commitment to quality and innovation makes this model a preferred choice for those seeking dependable heating systems. Whether for new installations or replacements, the Weil-McLain 550-110-260/02002 delivers exceptional performance and value.