Linear Boiler installation instructions Breeching and Venting

Page 14

PAGE 14

BIASI B/40

 

 

10. Breeching and Venting:

The B-40 Linear boiler is a high efficiency unit that requires proper venting. The boiler must be vented to the outdoors by means of a tile lined masonry or an approved pre-fabricated chimney of the size and height recommended by the manufacturer or by a listed "power venting" unit which provides draft by mechanical venting .

The chimney discharge opening must be located at least 24 inches above any part of the building structure within 10 feet of the chimney. Be sure the chimney and smoke pipe don't become obstructed by squirrels, bird nests, soot buildup, chimney liner deterioration, etc. The "power ventor" system should be installed on the leeward side of the building. Very specific requirements must be met concerning clearances from combustibles and distances from doors and windows. Please consult with manufacturer of "power ventor" for this information. In any case, the "ventor" must be installed by a licensed burner mechanic and done in accordance with local codes. The B-40 boiler is a very low stack temperature boiler (between 320 and 400F gross stack temp.) so caution should be used when connecting to an outside built chimney. Should you have concern that the flue gases could condense, then you should consider using a listed, "power venting" unit. If "power venting" is used to discharge flue gases, then the power vent unit should be equipped with a postpurge control as well as delay-off, timing control to prevent problems with fogging and nozzle post drip.

Note: 88% steady state efficiency is achieved when flue gas contains over 12.5% CO2 and the gross stack temp. is below 350F.

The smoke-pipe connection from the boiler to the chimney should be as short as possible, with a minimum number of elbows. The vent pipe must have a vertical rise of at least 1/4 inch per foot of horizontal run. The vent pipe must be of the same diameter as the flue outlet on the boiler. The chimney connector should have a minimum thickness of 24 gauge, corrosion resistant (galvanized) steel, assembled with a minimum of three (3) sheet-metal screws, and sealed with high temperature silicon at each joint. In most cases a barometric draft control isn't recommended as the B-40 is designed to be pressure-fired. However, one may be needed if the boiler is being used in a high draft situation.

Image 14
Contents Linear Boiler Page Table of Contents Important Information Please read this page carefullyBiasi B/40 Conforming to Codes and Regulations WeightGeneral Information Combustion Air Supply Boiler LocationBoiler Block Assembly Installation of Boiler Trim ComponentsBiasi B/40 Burner Setup Burner ManufacturerFt 3/hr = 3600/sec. Per rev.*Size of gas meter Installation of Sediment Trapand Burner Supply Gas Line PipingInstallation of Sediment Trapand Burner Supply Breeching and Venting Blocked Flue Switch PipingBiasi B/40 Boiler Jacket Assembly Boiler Components Parts Vega B40 SeriesWiring Control Panel Description Relay Circulator Circulator Relay Control Panel Wiring Diagram for Riello Oil Burner Control Panel Wiring Diagram for Heat Wise Gas Burners Maintenance CommissioningInstaller Notes System CheckoutBiasi B/40 Biasi B/40 Warranty For Biasi B40 Series Commercial Cast-Iron Water Boilers