Lochinvar 399 operation manual 3AClearance to Gravity Air Inlets

Page 24

Installation & Operation Manual

4 Sidewall direct venting

Vent/air termination – sidewall

Figure 4-1CAlternate Stainless Steel Vent Termination

-Typical Stainless Steel Sidewall Termination of Air and Vent Models 399 - 600 w/Field Supplied Fittings, Utilizing FasNSeal’s Hood Intake. Available Through FasNSeal Only

Figure 4-2BAlternate Stainless Steel Sidewall Termination Models 700 - 800 w/Field Supplied Fittings

BIRD SCREEN

TO BOILER

INTAKE AIR

CONNECTION

12" (305 MM) MIN 15" (381 MM) MAX

TO BOILER INTAKE AIR CONNECTION

FROM BOILER VENT PIPE CONNECTION

12" (305 MM) MIN 15" (381 MM) MAX

FROM BOILER

VENT PIPE

CONNECTION

12" (305 MM) MIN

Figure 4-1DAlternate PVC/CPVC/SS Vent Termination

-Typical Stainless Steel Sidewall Termination of Air and Vent Models 399 - 600 w/Field Supplied Fittings, Utilizing 90° Elbow Intake

TO BOILER

INTAKE AIR

CONNECTION

FROM BOILER

 

VENT PIPE

 

CONNECTION

12" MIN

 

15" MAX

12" MIN

BIRD SCREEN

Figure 4-2AAlternate PVC/CPVC Sidewall Termination Models 399 - 800 w/Field Supplied Fittings

12" (305 MM) MIN

NOTICE PVC/CPVC or ABS is acceptable air inlet pipe material.

5.Maintain clearances as shown in FIG.’s 4-1A thru 4-4B, pages 23 thru 25. Also maintain the following:

a.Vent must terminate:

At least 6 feet (1.8 m) from adjacent walls.

No closer than 12 inches (305 mm) below roof overhang.

At least 7 feet (2.1 m) above any public walkway.

At least 3 feet (.9 m) above any forced air intake within 10 feet (3 m).

No closer than 12 inches (305 mm) below or horizontally from any door or window or any other gravity air inlet.

b.Air inlet must terminate at least 12 inches (305 mm) above grade or snow line; at least 12 inches (305 mm) below the vent termination (FIG. 4-1B); and the vent pipe must not extend more than 24 inches (610 mm) vertically outside the building.

c.Do not terminate closer than 4 feet (1.2 m) horizontally from any electric meter, gas meter, regulator, relief valve, or other equipment. Never terminate above or below any of these within 4 feet (1.2 m) horizontally.

6.Locate terminations so they are not likely to be damaged by foreign objects, such as stones or balls, or subject to buildup of leaves or sediment.

TO BOILER

INTAKE AIR

CONNECTION

FROM BOILER

VENT PIPE

CONNECTION

24

BIRD SCREEN

12" (305 MM) MIN 15" (381 MM) MAX

BIRD SCREEN

12" (305 MM) MIN

Figure 4-3AClearance to Gravity Air Inlets

12"

MIN.

VENT / AIR

TERMINATION

12" MIN.

12" MIN.

Image 24
Contents Models 399 Save this manual for future referenceContents When servicing boiler Please read before proceedingKnight XL How it works Air pressure switch Pump relay board ModelModels 600 Ratings Knight XL Boiler =B=R RatingInstallation must comply with Closet and alcove installationsDetermine boiler location Before locating the boiler, checkFor closet installations, Cpvc or TOPResidential garage installation Provide air openings to roomVent and air piping Flooring and foundationWhen using an existing vent system to install a new boiler Products to avoidAreas likely to have contaminants When removing a boiler from existing common vent system Prepare boiler Remove boiler from wood palletModel Gas conversionsLeveling the boiler Models 600General venting Direct venting options Vertical Vent Install vent and combustion air piping Requirements for installation in CanadaInstalling vent or air piping General ventingPVC/CPVC air intake/vent connections Approved Stainless Steel Vent ManufacturersMake Air inlet pipe materials Stainless steel ventFasNSeal Saf-T Vent Stainless steel air intake/vent connectionsOptional room air Removing from existing ventModel Description Kit Number Air contaminationIf using the alternate sidewall termination Sidewall direct ventingVent/air termination sidewall Determine location3AClearance to Gravity Air Inlets Prepare wall penetrations Bird Screen TypicalPrepare wall penetrations Alternate Field Supplied Option Multiple vent/air terminationsTermination and fittings Sidewall termination installation Description and usage9Concentric Vent Dimensional Drawing Models 399 11Concentric Vent Sidewall Attachment Multiventing sidewall terminationsVertical direct venting Vent/air termination verticalPrepare roof penetrations 2Vertical Terminations with Multiple BoilersVertical termination installation 4Concentric Vertical TerminationMultiventing vertical terminations Mm see -9,Hydronic piping Hydronic piping Flow switch adjustment Near boiler piping connectionsCirculator sizing Head Feet Pressure20F 25F 30F 35F 399 500 600 700 800Near boiler piping components 7Single Boiler Primary/Secondary Piping Number of Units Model Manifold Pipe Sizes in Inches mm Connecting gas supply piping Gas connectionsNatural gas Propane GasNominal Natural Gas Pipe Capacity Chart Check inlet gas supplyIron Pipe Length of Pipe in Straight FeetGas valve replacement Gas PressureField wiring Installation must comply withLine voltage connections Outdoor temperature sensor Auxiliary device proving switchHigh gas pressure switch Low gas pressure switchAlarm contacts Wiring of the cascadeSystem supply sensor Boiler management system3Low Voltage Field Wiring Connections Condensate disposal Condensate drainFreeze protection when used Start-upCheck/control water chemistry Fill and test water systemCheck for gas leaks Check thermostat circuitsInspect/fill condensate system Inspect/check condensate lines and fittingsFinal checks before starting the boiler Start the boilerIf boiler does not start correctly Check system and boilerFor Your Safety Read Before Operating Set space heating operation Natural Gas PropaneConfiguration of the cascade Set domestic hot water DHW operationOperating information GeneralProtection features Boiler temperature regulation Outdoor reset operation, if usedCascade DHW, Night Setback, and Ramp Delay operation with Cascade Sequence of the cascadeSequence of operation BLR IgnitionKnight XL control module ShutdownAccess modes InstallerUser To save parameters and exit programmingService StandbySet Point Met PrepurgeSYS ***.*F Control will display the actual fan motor RPMDelay 10V in **.VdcOperation of the cascade Maintenance Maintenance and annual startup Service technicianOwner maintenance Maintenance Address reported problemsClean condensate trap Check all piping for leaks Inspect boiler areaFlue vent system and air piping Check water systemCheck expansion tank Check boiler relief valveCheck ignition ground wiring Check all boiler wiringCheck control settings Inspect ignition and flame sense electrodesCheck flame signal Cleaning boiler heat exchangerReview with owner Model Kit Part Component Number DescriptionDiagrams High Voltage2Ladder Diagram Page Page KBX-I-O Rev H
Related manuals
Manual 72 pages 15.81 Kb

399 specifications

Lochinvar 999 - 750, CF-CH(E)-i&s-08,399 is a cutting-edge boiler designed for commercial heating applications. With its robust construction and high efficiency, this model stands out in the crowded market of heating solutions.

One of the main features of the Lochinvar 999 - 750 is its exceptional thermal efficiency rating. The unit incorporates advanced condensing technology that allows it to recover heat from flue gases, which helps in achieving efficiency levels of up to 99%. This efficiency not only reduces energy consumption but also lowers operational costs, making it an excellent investment for businesses looking to minimize their carbon footprint.

The boiler is designed to provide a powerful output of 750 kW, ensuring it meets the heating demands of larger buildings or commercial spaces. Its capacity makes it suitable for a range of applications including schools, hospitals, and industrial facilities. Moreover, the unit features a built-in cascading system that enables multiple boilers to be connected, enhancing system reliability and flexibility.

In terms of technology, the Lochinvar 999 - 750 is equipped with a user-friendly touchscreen interface. This innovative control system allows operators to monitor and adjust settings with ease, providing real-time performance data and alerts for maintenance needs. The intelligent controls optimize operation to match the heating load, further enhancing energy efficiency.

Safety is a top priority with this model. It is built with multiple safety features such as automatic shut-off valves, pressure relief valves, and flame monitoring systems, ensuring safe operation under various conditions. The unit also adheres to stringent industry standards and regulations, making it a reliable choice for commercial applications.

Furthermore, the Lochinvar 999 - 750 is designed with serviceability in mind. Its compact footprint and accessible components simplify maintenance, reducing downtime and associated costs. The unit also supports a variety of fuel sources, including natural gas, propane, and biodiesel, providing flexibility to meet different facility requirements.

In summary, the Lochinvar 999 - 750, CF-CH(E)-i&s-08,399 represents a blend of efficiency, reliability, and safety in commercial heating. Its advanced technologies and thoughtful design make it a powerful solution for various heating needs, making it an ideal choice for businesses aiming for excellence in energy management and operational efficiency.