Lochinvar 399 operation manual Knight XL How it works

Page 4

Installation & Operation Manual

The Knight XL - How it works...

1.Stainless steel heat exchanger

Allows system water to flow through specially designed coils for maximum heat transfer, while providing protection against flue gas corrosion. The coils are encased in a jacket that contains the combustion process.

2.Heat exchanger access cover

Allows access to the combustion side of the heat exchanger coils.

3.Blower

The blower pulls in air and gas through the venturi (item 5). Air and gas mix inside the blower and are pushed into the burner, where they burn inside the combustion chamber.

4.Gas valve

The gas valve senses the negative pressure created by the blower, allowing gas to flow only if the gas valve is powered and combustion air is flowing.

16.SMART Control Module

The SMART Control responds to internal and external signals and controls the blower, gas valve, and pumps to meet the heating demand.

17.Automatic air vent

Designed to remove trapped air from the heat exchanger coils.

18.Air intake adapter

Allows for the connection of the PVC air intake pipe to the boiler.

19.High voltage junction box

The junction box contains the connection points for the line voltage power and all pumps.

20.Boiler drain port

Location from which the heat exchanger can be drained.

5.Venturi

The venturi controls air and gas flow into the burner.

6.Flue gas sensor

This sensor monitors the flue gas exit temperature. The control module will modulate and shut down the boiler if the flue gas temperature gets too hot. This protects the flue pipe from overheating.

7.Boiler outlet temperature sensor

This sensor monitors boiler outlet water temperature (system supply). If selected as the controlling sensor, the control module adjusts boiler firing rate so the outlet temperature is correct.

8.Boiler inlet temperature sensor

This sensor monitors return water temperature (system return). If selected as the controlling sensor, the control module adjusts the boiler firing rate so the inlet temperature is correct.

9.Temperature and pressure gauge (field installed, not shown)

Monitors the outlet temperature of the boiler as well as the system water pressure.

10.Electronic display

The electronic display consists of 7 buttons and a dual line 32- character liquid crystal display.

11.Flue pipe adapter

Allows for the connection of the PVC vent pipe system to the boiler.

12.Burner (not shown)

Made with metal fiber and stainless steel construction, the burner uses pre-mixed air and gas and provides a wide range of firing rates.

13.Water outlet (system supply)

A 1-1/2" or 2" NPT (depending on the model) water connection that supplies hot water to the system.

14.Water inlet (system return)

A 1-1/2" or 2" NPT (depending on the model) water connection that returns water from the system to the heat exchanger.

15.Gas connection pipe

Threaded pipe connection, either 1" or 1-1/2", depending on the model. This pipe should be connected to the incoming gas supply for the purpose of delivering gas to the boiler.

21.Low voltage connection board

The connection board is used to connect external low voltage devices.

22.Low voltage wiring connections (knockouts)

Conduit connection points for the low voltage connection board.

23.Condensate drain connection

Connects the condensate drain line to a 1/2" PVC union.

24.Access cover - front

Provides access to the gas train and the heat exchanger.

25.Ignition electrode

Provides direct spark for igniting the burner.

26.Flame inspection window

The quartz glass window provides a view of the burner surface and flame.

27.Gas shutoff valve

Manual valve used to isolate the gas valve from the gas supply.

28.High limit

Device that monitors the outlet water temperature. If the temperature exceeds its setting, it will break the control circuit, shutting the boiler down.

29.Relief valve

Protects the heat exchanger from an over pressure condition. The relief valve will be set at 50 PSI.

30.Flame sensor

Used by the control module to detect the presence of burner flame.

31.Line voltage wiring connections (knockouts)

Conduit connection points for the high voltage junction box.

32.Top panel

Removable panel to gain access to the internal components.

33.Power switch

Turns 120 VAC ON/OFF to the boiler.

34.Leveling legs

Used to allow the heat exchanger to be leveled. This is needed for the proper draining of the condensate from the combustion chamber.

35.Air shroud (Model 500 only)

The air shroud controls air and gas flow into the burner.

4

Image 4
Contents Models 399 Save this manual for future referenceContents When servicing boiler Please read before proceedingKnight XL How it works Air pressure switch Pump relay board ModelModels 600 Ratings Knight XL Boiler =B=R RatingInstallation must comply with Closet and alcove installationsDetermine boiler location Before locating the boiler, checkFor closet installations, Cpvc or TOPResidential garage installation Provide air openings to roomVent and air piping Flooring and foundationProducts to avoid When using an existing vent system to install a new boilerAreas likely to have contaminants When removing a boiler from existing common vent system Prepare boiler Remove boiler from wood palletModel Gas conversionsLeveling the boiler Models 600General venting Direct venting options Vertical Vent Install vent and combustion air piping Requirements for installation in CanadaInstalling vent or air piping General ventingApproved Stainless Steel Vent Manufacturers PVC/CPVC air intake/vent connectionsMake Air inlet pipe materials Stainless steel ventFasNSeal Saf-T Vent Stainless steel air intake/vent connectionsOptional room air Removing from existing ventModel Description Kit Number Air contaminationIf using the alternate sidewall termination Sidewall direct ventingVent/air termination sidewall Determine location3AClearance to Gravity Air Inlets Prepare wall penetrations Bird Screen TypicalMultiple vent/air terminations Prepare wall penetrations Alternate Field Supplied OptionTermination and fittings Sidewall termination installation Description and usage9Concentric Vent Dimensional Drawing Models 399 11Concentric Vent Sidewall Attachment Multiventing sidewall terminationsVertical direct venting Vent/air termination verticalPrepare roof penetrations 2Vertical Terminations with Multiple BoilersVertical termination installation 4Concentric Vertical TerminationMultiventing vertical terminations Mm see -9,Hydronic piping Hydronic piping Near boiler piping connections Flow switch adjustmentCirculator sizing Head Feet Pressure20F 25F 30F 35F 399 500 600 700 800Near boiler piping components 7Single Boiler Primary/Secondary Piping Number of Units Model Manifold Pipe Sizes in Inches mm Connecting gas supply piping Gas connectionsNatural gas Propane GasNominal Natural Gas Pipe Capacity Chart Check inlet gas supplyIron Pipe Length of Pipe in Straight FeetGas valve replacement Gas PressureInstallation must comply with Field wiringLine voltage connections Outdoor temperature sensor Auxiliary device proving switchHigh gas pressure switch Low gas pressure switchAlarm contacts Wiring of the cascadeSystem supply sensor Boiler management system3Low Voltage Field Wiring Connections Condensate disposal Condensate drainFreeze protection when used Start-upCheck/control water chemistry Fill and test water systemCheck for gas leaks Check thermostat circuitsInspect/fill condensate system Inspect/check condensate lines and fittingsFinal checks before starting the boiler Start the boilerIf boiler does not start correctly Check system and boilerFor Your Safety Read Before Operating Set space heating operation Natural Gas PropaneConfiguration of the cascade Set domestic hot water DHW operationOperating information GeneralProtection features Outdoor reset operation, if used Boiler temperature regulationCascade DHW, Night Setback, and Ramp Delay operation with Cascade Sequence of the cascadeSequence of operation BLR IgnitionKnight XL control module ShutdownAccess modes InstallerUser To save parameters and exit programmingService StandbySet Point Met PrepurgeSYS ***.*F Control will display the actual fan motor RPMDelay 10V in **.VdcOperation of the cascade Service technician Maintenance Maintenance and annual startupOwner maintenance Maintenance Address reported problemsClean condensate trap Check all piping for leaks Inspect boiler areaFlue vent system and air piping Check water systemCheck expansion tank Check boiler relief valveCheck ignition ground wiring Check all boiler wiringCheck control settings Inspect ignition and flame sense electrodesCheck flame signal Cleaning boiler heat exchangerReview with owner Model Kit Part Component Number DescriptionDiagrams High Voltage2Ladder Diagram Page Page KBX-I-O Rev H
Related manuals
Manual 72 pages 15.81 Kb

399 specifications

Lochinvar 999 - 750, CF-CH(E)-i&s-08,399 is a cutting-edge boiler designed for commercial heating applications. With its robust construction and high efficiency, this model stands out in the crowded market of heating solutions.

One of the main features of the Lochinvar 999 - 750 is its exceptional thermal efficiency rating. The unit incorporates advanced condensing technology that allows it to recover heat from flue gases, which helps in achieving efficiency levels of up to 99%. This efficiency not only reduces energy consumption but also lowers operational costs, making it an excellent investment for businesses looking to minimize their carbon footprint.

The boiler is designed to provide a powerful output of 750 kW, ensuring it meets the heating demands of larger buildings or commercial spaces. Its capacity makes it suitable for a range of applications including schools, hospitals, and industrial facilities. Moreover, the unit features a built-in cascading system that enables multiple boilers to be connected, enhancing system reliability and flexibility.

In terms of technology, the Lochinvar 999 - 750 is equipped with a user-friendly touchscreen interface. This innovative control system allows operators to monitor and adjust settings with ease, providing real-time performance data and alerts for maintenance needs. The intelligent controls optimize operation to match the heating load, further enhancing energy efficiency.

Safety is a top priority with this model. It is built with multiple safety features such as automatic shut-off valves, pressure relief valves, and flame monitoring systems, ensuring safe operation under various conditions. The unit also adheres to stringent industry standards and regulations, making it a reliable choice for commercial applications.

Furthermore, the Lochinvar 999 - 750 is designed with serviceability in mind. Its compact footprint and accessible components simplify maintenance, reducing downtime and associated costs. The unit also supports a variety of fuel sources, including natural gas, propane, and biodiesel, providing flexibility to meet different facility requirements.

In summary, the Lochinvar 999 - 750, CF-CH(E)-i&s-08,399 represents a blend of efficiency, reliability, and safety in commercial heating. Its advanced technologies and thoughtful design make it a powerful solution for various heating needs, making it an ideal choice for businesses aiming for excellence in energy management and operational efficiency.