C
B
| FINISHING COMMISSIONING - | |
|
|
|
| APPLIANCE | |
| 1 Refit the top panel and press down to | |
|
| compress the seal when fitting the |
A |
| securing screws (A). |
| 2 Push the front panel up behind the top | |
A |
| panel and push in at the base to secure |
|
| the screws (B) with the tool provided. |
|
| Always apply pressure at the edges of the |
|
| panels when securing to avoid accidental |
1 |
| damage. |
2
B
Handover:
Complete the guarantee registration card, combustion record (page 49) and a CD11 or
Kan equivalent commissioning form.
Set up the controls and show the user how to operate all the controls shown in the User Guide, and all system controls.
Where applicable, instruct the customer how to repressurise the system.
If the appliance is unused and exposed to freezing conditions, shut off all the mains supplies and drain the system and boiler to prevent damage to the system and boiler.
NOTE: Release drain point (K) to drain the secondary heat exchanger.
COMMISSIONING
|
| 36 |
|
| |
INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER GREENSTAR HEATSLAVE EXTERNAL | FINISHING COMMISSIONING - | 31 |
8 716 113 389b (09/07) |