Ariston 47-116-08. 47-116-09, 47-116-13, 41-116-01 installation instructions Maintenance

Page 26

5.MAINTENANCE

5.Adjust the soft-light feature;

6.Adjust the delayed lighting feature for the heating system (can be set from 0 to 2 mins.).

It is recommended that the following checks be made on the boiler at least once a year:

1 - Check the seals for the water connections; replacement of any faulty seals.

2 - Check the gas seals; replacement of any faulty gas seals.

3 - Visual check of the entire unit.

4 - Visual check of the combustion process or analysis of flue gas (see ref 3.6) and cleaning of the burners if needed.

5 - If called for by check no. 3, dismantling and cleaning of the combustion chamber.

6 - If called for by check no. 4, dismantling and cleaning of the injectors.

7 - Visual check of the primary heat exchanger:

-check for overheating in the blade assembly;

-clean the exhaust fan if needed.

8 - Adjustment of the flow rate of the gas: flow rate for lighting, partial load and full load.

9- Check of the heating safety systems:

-safety device for maximum temperature;

-safety device for maximum pressure.

10- Check of the gas safety systems:

-safety device for lack of gas or flame ionisation (detection electrode);

-safety device for gas cock.

11- Check of the electrical connection (make sure it complies with the instructions in the manual).

12- Check of domestic hot water production efficiency (delivery rate and tem- perature)

13- Check of the general performance of the unit.

14- General check of the discharge/ventilation of the combustion by- products.

26

B004

Image 26
Contents Leave These Instructions Adjacent to the GAS Meter Table of Contents General Information General InformationTechnical Information Genus 27 Rffi System Overall ViewSiting the Appliance InstallationReference Standards Overall Dimensions ClearancesGas Connection Mounting the ApplianceElectrical Connection Pipe Work Safety Valve DischargeWater Connections View of the Boiler Connections By-passMains Water Feed Central Heating Flue ConnectionsAir Release Points FillingTower Flue Components 80 mm B004 KW 27 kW Exhaust/Air Maximum Extension Room Thermostat Connection Electrical Diagram ColoursGenus 27 Rffi System CN202 Water Circuit Diagram Removing the Casing CommissioningInitial Preparation Filling the Heating SystemControl Panel Summer/Winter/Flue Analysis ModesInitial Start-up Operational Adjustments Checks to be run before initial start-up are as follows Combustion Analysis Fume Discharge MonitoringBoiler Safety Systems GAS Adjustments Changing the Type of GasMaintenance Wiring Diagram for Two Heating Zones MiscellaneousWiring Diagram for Connection to Ariston Unvented Cylinder TypicalB004 B004 B004 Technical Service Hotline 01494