9)Pitch of Horizontal Piping - Pitch all horizontal piping so that any condensate which forms in the piping will run towards the boiler:

Pitch Crown horizontal concentric venting 5/8” per foot

Pitch Stainless steel venting 1/4” per foot.

10)Supporting Pipe - Vertical and horizontal sections of pipe must be properly supported:

Support Crown concentric venting near the female end of each straight section of pipe.

Exception: Vertical runs of concentric pipe in an unused chinmey (Figure 7.36) need only be supported at the terminal and at the base of the run.

• Support stainless steel venting as called for by the vent manufacturer’s instructions.

FIGURE 7.7: SNORKEL TERMINAL CONFIGURATION

18

Image 9
Contents Page VII Venting Page Summary of Horizontal Venting Options Horizontal Concentric Venting Vent Option 1,3 Vent Option Manufacturer Vent Size Component Part Number 6c Positioning Vent Terminal Under Overhangs Snorkel Terminal Configuration VENT/ AIR Intake Fitting Equivalent Length 10 Vertical Twin Pipe Vent System Vent Option Removing an Existing Boiler From a Common Chimney Page 21 Dimension L 22 Cutting Outer Pipe 25 Attaching 60/100mm Terminal Section 30a Cuttable Straight Section 31 Cutting Straight Pipe 32a Joining Cuttable Pipe 33a Dimension L, 80/125mm Horizontal Terminal 33c Cutting Inner Pipe of 80/125mm Horizontal Terminal 34 Installation of Snorkel Terminal 35a Dimension H 35b Cutting Vertical Terminal 36 Chimney Chase Installation Assembly of Stainless Steel Venting 47 CORR/GUARD Connection to Vent Collar