4. Install Firestops

4. Install Firestops

For Horizontal Runs - Firestops are REQUIRED on both sides of a combustible wall through which the vent passes.

NOTE: Model DVP-TRAP does not need an exterior fir- estop on an exterior combustible wall.

To install firestops for horizontal runs that pass through either interior or exterior walls:

Cut a 10-inch by 12-inch (254mm X 305mm) hole through the wall.

NOTE: The center of the hole is one (1) inch (25.4mm) above the center of the horizontal vent pipe.

Position the firestops on both sides of the hole previ- ously cut and secure the firestops with nails or screws.

The heat shields of the firestops MUST BE placed to- wards the top of the hole.

Continue the vent run through the firestops.

NOTE: There must be NO INSULATION or other combustibles inside the framed firestop opening.

10"

INTERIOR

WALL SHIELD

12"

Figure 15. 10" x 12" Hole and Vent Pipe

HEAT SHIELD

TRIM HEAT SHIELD IF TOO LONG, ADD TO SHIELD IF TOO SHORT

EXTERIOR

FIRESTOP

INTERIOR

FIRESTOP

Figure 16. Heat Shield, Interior & Exterior Firestops

For Vertical Runs - One ceiling firestop is REQUIRED at the hole in each ceiling through which the vent passes.

To install firestops for vertical runs that pass through ceilings:

Position a plumb bob directly over the center of the verti- cal vent component.

Mark the ceiling to establish the centerpoint of the vent.

Drill a hole or drive a nail through this centerpoint.

Check the floor above for any obstructions, such as wir- ing or plumbing runs.

Reposition the fireplace and vent system, if necessary, to accommodate the ceiling joists and/or obstructions.

Cut an 10-inch X 10-inch (254mm X 254mm) hole through the ceiling, using the centerpoint previously marked.

Frame the hole with framing lumber the same size as the ceiling joists.

10" (254mm)

10" (254mm)

 

 

CHIMNEY

 

HOLE

NEW

EXISTING CEILING

JOISTS

FRAMING

MEMBERS

 

CEILING

 

Figure 17. 10" x 10" Hole & New Framing Members

If the area above the ceiling is NOT an attic, position and secure the ceiling firestop on the ceiling side of the previously cut and framed hole.

NOTE: There must be NO INSULATION or other combustibles inside the framed firestop opening.

JOIST

CEILING

NAILS (4 REQUIRED)

CEILING FIRESTOP

Figure 18. Ceiling Firestop (Ceiling Side)

18

Heat & Glo • GEM42 • 371-900 Rev. N • 2/05

Image 18
Contents GEM42 ModelInstallers Guide Underwriters Laboratories ListedREAD and UNDERSTAND all instructions carefully SAFETY AND WARNING INFORMATIONThis gas fireplace and vent assembly MUST be DO NOT USE this appliance if any part has beenService Parts Lists TABLE OF CONTENTSSafety and Warning Information Section 3 Installing the Fireplace5 Log set assembly Service PartsGEM42 NG, LP Exploded Parts DiagramService Parts List / Liste des pièces de rechange GEM42ACCESSORIES / ACCESSOIRES Valve Assembly Intermittent Pilot Ignition1Approvals and Codes Installation CodesHigh Altitude Installations Appliance CertificationIntroducing the Heat & Glo Gas Fireplaces Pre-install Preparation2Getting Started ANY SUCH ACTION MAY POSSIBLY CAUSE A FIRE HAZARDFigure 1. Diagram of the GEM42 Heat & Glo GEM42 371-900 Rev. N 2/05Step 1. Locating the Fireplace 3Installing the FireplaceConstructing the Fireplace Chase Fireplace Dimensions, Locations47-1/2” Step 2. Framing the FireplaceFigure 3. Framing Dimensions 47-3/4”NOTE PIPES OVERLAP 1-1/4 INCHES AT EACH JOINT DVP90STTEMS OR COMPONENTS MAY BE USED Step 3. Installing the Vent SystemA. Vent System Approvals Identifying Vent ComponentsFlue Restrictor Instructions Pilot Shield AdjustmentSTRAIGHT UP VERTICAL VENTING V FT 40 MAX. 12.4 MELBOWS VENTING WITHTWO 2 90 o VENTING WITH ONE 1 90 ELBOWVENTING WITH THREE 3 90 ELBOWS V FTH FT H + H 1 FTVenting Out the Top Vent B. Installing Vent Components3. Install Support Brackets 1. Attach the First Vent Component to the Starting CollarsFigure 15. 10 x 12 Hole and Vent Pipe 4. Install FirestopsCut a 10-inch by 12-inch 254mm X 305mm hole through the wall Figure 16. Heat Shield, Interior & Exterior FirestopsWARNING THE TERMINATION CAP MUST BE C. Vent TerminationAttic Firestop POSITIONED SO THAT THE ARROW IS POINT- ING UPnot to be installed above a gas = AREA WHERE TERMINAL IS NOT PERMITTEDelectrical service meter/regulator assembly withinFigure 22. Minimum Height from Roof to Lowest Discharge Opening Step 4. Positioning, Leveling and Securing the FireplaceWARNING MAJOR U.S. BUILDING CODES SPECIFY MINIMUM CHIMNEY AND/OR Figure 23. Proper PositioningHeat-Zone Kit Step 5. Installing the Optional Heat-Out or Heat-Zone KitsHeat-Out Kit Step 6 The Gas Control SystemPressure Step 7. The Gas Supply LineStep 8. Gas Pressure Requirements Natural GasIntermittent Pilot Ignition IPI Wiring 3 Volt Transformer Step 9. Wiring the FireplaceFigure 26. Intermittent Pilot Ignition IPI Wiring Diagram Operation with Battery Back-upWARNING WHEN FINISHING THE FIREPLACE Step 10. FinishingFigure 27. Fan Wiring Diagram FINISH WALL MATERIALFigure 31. Facing Template Dimensions IMPORTANT INSTALLATION NOTEFacing Requirements Facing Thickness from 3/4” to 1-1/4”Figure 34. Glass Assembly Step 11. Installing Trim, Logs and Ember MaterialInstalling the Trim Glass Specifications GEM42 CERAMICStep 13. Lighting the Fireplace After the InstallationStep 12. Before Lighting the Fireplace Double-check for faulty componentsCleaning Flame Sensor Rod IPI Systems Frequency Annually Fireplace Maintenance4Maintaining and Servicing Your Fireplace Cleaning Glass Door