Sears 153.332040, 153.332060 Vertical Vent Through Roof, Vertical Vent Termination Restrictions

Page 19

FIGURE23.

This unit can vent through 2", 3" or 4" nonmetallic pipe and fittings.

The vent pipe installation can be started from either the blower discharge or the termination wall. Keep in mind the total vent system (pipe and elbows) when installing the vent system, see VENTING AND INSTALLATIONAND MAXIMUM VENTLENGTHS, page 17.

FIGURE24.

The vent terminal should be kept as close as possible to the outside wall, but you need to allow at least 1.5" (3.8 cm) of pipe past the wall, for the wall flange and vent terminal to mount on the pipe.

Before the vent terminal is installed, caulk (not supplied) around the pipe on the exterior wall and install the optional wall flange. The flange can be held to the outside wall by placing some of the caulking on the back of the flange. The wall flange is supplied for decorative purposes only and is not a requirement for the vent termination (if not needed by the installer).

VERTICAL VENT THROUGH ROOF

This unit is approved for venting through the roof with the type vent terminal that is included with the unit. A proper flashing or “BOOT” should be used to seal the pipe where it exits the roof.

The total vent system should not exceed that which is specified, see VENTINGAND INSTALLATION, page 17.

All of the pipe should be secured as per the instructions in the instructions

VERTICAL VENT TERMINATION RESTRICTIONS

1.Minimum of twelve 12" (30.5 cm) above the roof or twelve 12" (30.5 cm) above the anticipated snow level. Provide proper support for all pipe protruding through the roof.

FIGURE25.

2.4' (1.2 m) from or 1' (0.3 m) above any gable, dormer, or other roof structure with access to interior of building (i.e.-vent, window etc.).

in the VENTINGAND INSTALLATION, page 17.

3. 3' (0.9 m) above any forced air inlet located within 10' (3.0 m).

19

Image 19
Contents Economizer 6 GAS Water Heater Important Definitions Safe INSTALLATION, USE and ServiceSafety Precautions Table of Contents Preparing for the Installation Product SpecificationsCustomer Responsibilities Materials Needed Materials and Basic Tools NeededNatural HOT Surface Igniter & Main Burner Typical InstallationPropane HOT Surface Igniter & Main Burner Removing the Old Water Heater Installation InstructionsFacts to Consider about the Location Insulation Blankets ALL AIR from Inside Buildings See Hotter Water can Scald Water PipingValve and Pipe Insulation if supplied GAS Piping Filling the Water Heater Blower Assembly InstallationSequenceofinstallation Sediment TrapsPage Maximum Vent Lengths Vent Connections to Blower AssemblyVenting and Installation CondensationVenting Vent Terminal InstallationVertical Vent Termination Restrictions Vertical Vent Through RoofRecommended BRUSH* Size for Primer Cement Applications Vent Pipe PreparationStepg StepbStepe StepfWhat to do if YOU Smell GAS PowerbeforeservicingOperating Instructions Do not try to light the burner by handTemperature Setting Burns on Adult Skin Temperature RegulationSMOKE/ODOR For Your InformationStart UP Conditions CondensateBurner Operation and Inspection Service and AdjustmentOperational Conditions Venting System InspectionAnode ROD Inspection Burner CleaningTEMPERATURE-PRESSURE Relief Valve Operation HousekeepingService Drain Valve Washer ReplacementDraining Leakage Checkpoints LED Status Troubleshooting GuidelinesTroubleshooting Guidelines Model Numbers Part Description 153.332040 153.332050 Repair Parts ListBurner Assembly Outer Door Alternate Economizer 6 GAS Water HeaterSears Installation Service Year Limited Warranty on Water HeaterYear Exclusive Kenmore Labor Warranty Warranty Service