LG Electronics 395CAV installation instructions ÐControl Board, Ð9Ð

Page 9

 

BLOWER OFF DELAY

 

ADJUSTMENT SWITCH

 

G

24V THERMOSTAT

 

TERMINALS

 

R

 

 

 

Y

 

TEST/TWIN

W

HUMIDIFIER TERMINAL

Com

 

24V

(24-VAC 0.5 AMP MAX)

 

HUM

LED OPERATION &

 

 

 

 

DIAGNOSTIC LIGHT

 

 

HARNESS CONNECTOR

SEC-1

24V TRANSFORMER SEC-2

 

3-AMP FUSE

SPARE 1

COOL

BLOWER SPEED

HEAT

 

SELECTION TERMINALS

 

SPARE 2

 

EAC 1 (BLACK)

 

EAC-ELECTRONIC AIR CLEANER

 

TERMINALS (115-VAC 1.5 AMP MAX)

115-VAC (L1)

EAC 2 (WHITE)

POWER

115-VAC (L2) NEUTRAL

SUPPLY

CONNECTION

 

HOT SURFACE

INDUCER MOTOR

IGNITOR

CONNECTOR

CONNECTOR

 

A93052

Fig. 9ÐControl Board

A93053

Fig. 10ÐEAC Terminals on Control Board 1. Heating mode

When the wall thermostat "calls for heat," the R-W circuit closes. The furnace control performs a self-check, verifies the pressure switch contacts are open, and starts inducer motor.

a. Prepurge periodÐAs the inducer motor comes up to speed, the pressure switch contacts close to begin a 15-sec prepurge period.

b. Ignitor warm-upÐAt the end of the prepurge period, the ignitor is energized for a 17-sec ignitor warm-up period.

c. Ignition sequenceÐWhen the ignitor warm-up period is completed, the gas valve opens, permitting gas flow to the burners where it is ignited. After 5 sec, the ignitor is de-energized and a 2-sec flame-sensing period begins.

Ð9Ð

d. HUM terminal is energized with the gas valve. See accessories in the Electrical Connections section.

e.Flame-sensingÐWhen burner flame is sensed, the con- trol begins the blower on delay period and continues holding the gas valve open. If burner flame is not sensed, the control closes the gas valve and repeats ignition cycle.

NOTE: Ignition sequence will repeat 3 additional time before a lockout occurs. Lockout automatically resets after 3 hrs, or can be manually reset by turning 115v off (not at thermostat) for 3 sec minimum, then on again.

f.Blower on delayÐForty sec after burner flame is proven, the blower motor is energized on heating speed. Simul- taneously, the humidifier and electronic air cleaner terminals (HUM and Com for humidifier, EAC-1 and EAC-2 for electronic air cleaner) are energized. If jumper is on pin 6 and pin 9, blower on delay is 60 sec.

g.Blower off delayÐWhen the thermostat is satisfied, the circuit between R-W is broken, de-energizing the gas valve stopping gas flow to the burners. The blower motor and EAC remain energized 90, 135, 180, or 225 sec (depending on the blower off-time selection). The furnace is factory set for a 135-sec blower off delay.

h.Post-purgeÐThe inducer motor remains energized 5 sec after the burners are extinguished. If jumper is on pin 6 and pin 9, the post-purge period is 15 sec.

2.Cooling mode

When the thermostat "calls for cooling," R-G and R-Y circuits close. The R-Y circuit starts the outdoor condensing

Image 9
Contents Safety Considerations Electrostatic Discharge ESD PrecautionsÐ1Ð Ðminimum Clearances from Combustible MaterialsElectrostatic Discharge ESD Precautions Procedure ÐdimensionsÐ2Ð Unit Size Vent Conn SHIP. WT LBIntroduction LocationII. AIR for Combustion and Ventilation Confined Space Unconfined SpaceÐ4Ð 395CAV Furnace Minimum SQ FT with Input Btuh 2 FT CeilingÐ5Ð III. Filter ArrangementIV. Leveling Legs if Required GAS Piping Ðfilter InformationÐ6Ð Ðmaximum Capacity of PipeAccessories WiringVIII. START-UP, ADJUSTMENT, and Safety Check VI. Electrical ConnectionsÐelectrical Data Ð8ÐSequence of Operation Ð9Ð ÐControl BoardPCB → ÐUnit Wiring DiagramAdjustments Start-up ProceduresExample GAS Specific Gravity of Natural GAS Heat ValueBTU/CU FT → ÐRedundant Automatic Gas Control Valve Ðgas Rate CU FT/HRÐcanadian Orifice Size GAS SEA Level High AltitudeChecklist Ðspeed SelectorColor Speed Factory Attached to Service Training Ð16Ð