FIGURE16.

This unit can vent through 2", 3" or 4" nonmetallic pipe and fittings.

The vent pipe installation can be started from either the blower discharge or the termination wall. Keep in mind the total vent system (pipe and elbows) when installing the vent system, see VENTING AND INSTALLATION, pages 14 - 16.

FIGURE17.

The vent terminal should be kept as close as possible to the outside wall, but you need to allow at least 1.5" (3.8 cm) of pipe past the wall, for the wall flange and vent terminal to mount on the pipe.

Before the vent terminal is installed, caulk (not supplied) around the pipe on the exterior wall and install the optional wall flange. The flange can be held to the outside wall by placing some of the caulking on the back of the flange. The wall flange is supplied for decorative purposes only and is not a requirement for the vent termination (if not needed by the installer).

VERTICAL VENT THROUGH ROOF

This unit is approved for venting through the roof with the type vent terminal that is included with the unit. A proper flashing or “BOOT” should be used to seal the pipe where it exits the roof.

The total vent system should not exceed that which is specified, see VENTINGAND INSTALLATION, pages 14 - 16.

All of the pipe should be secured as per the instructions in the instructions

VERTICAL VENT TERMINATION RESTRICTIONS

1.Minimum of twelve 12" (30.5 cm) above the roof or twelve 12" (30.5 cm) above the anticipated snow level. Provide proper support for all pipe protruding through the roof.

FIGURE18.

2.4' (1.2 m) from or 1' (0.3 m) above any gable, dormer, or other roof structure with access to interior of building (i.e.-vent, window etc.).

in the VENTINGAND INSTALLATION, pages 14 - 16.

3. 3' (0.9 m) above any forced air inlet located within 10' (3.0 m).

17

Image 17 Contents
Residential GAS Water Heaters Important Definitions Safe INSTALLATION, USE and ServiceGeneral Safety Introduction Table of ContentsPropane HOT Surface Igniter & Main Burner Typical InstallationNatural HOT Surface Igniter & Main Burner Hotterwatercanscald Mixing Valve UsageFacts to Consider about the Location Locating the NEW Water HeaterInsulation Blankets ALL AIR from Outdoors See Figures 7, 8 ALL AIR from Inside Buildings SeeHotter Water can Scald Installing the NEW Water HeaterWater Piping Valve and Pipe Insulation if supplied TEMPERATURE-PRESSURE Relief ValveGAS Piping GAS Piping with Flexibleconnector Sequenceofinstallation Blower Assembly Installation Sediment Traps Filling the Water HeaterVenting and Installation Vent Connections to Blower AssemblyMaximum and Minimum Vent Lengths CondensateVenting Vent Terminal InstallationMasonry Side Walls Wooden Side WallsVertical Vent Termination Restrictions Vertical Vent Through RoofRecommended BRUSH* Size for Primer Cement Applications Vent Pipe PreparationStepe StepbStepf Step GPowerbeforeservicing WatertemperatureadjustmentDo not try to light the burner by hand What to do if YOU Smell GASTemperature Setting Burns on Adult Skin Temperature RegulationOperational Conditions For Your InformationStart UP Conditions Burner Cleaning Periodic MaintenanceVenting System Inspection Burner Operation and InspectionDrain Valve Washer Replacement TEMPERATURE-PRESSURE Relief Valve OperationAnode ROD Inspection DrainingLeakage Checkpoints ServiceNot Shown Optional Repair Parts ListBurner Assembly Drain PAN Outer Door Alternate Trouble Shooting Troubleshooting GuidelinesTroubleshooting Guidelines Page Page Claim Procedure Service and Labor ResponsibilityConditions and Exceptions Limitation on Implied WarrantiesTennessee Waltz Parkway Ashland City, TN