Electrical inspection checklist

The electrical inspection verifies that all electrical connections are secure and correct and that the cooling unit is properly grounded.

Electrical Hazard: All electrical wiring must comply with local and national codes and regulations.

Electrical Hazard: The equipment must be grounded (do not use a water-pipe ground).

Ensure that the:

Incoming voltages match the phase and voltage listed on the nameplate.

Electrical wiring complies with local and national codes and regulations.

Cooling unit is properly grounded.

Electrical connections are tight, including contactors, terminal blocks, controllers, switches, relays, auxiliary devices, and field connections.

Mechanical inspection checklist

The mechanical inspection verifies that all mechanical components and connections are secure and tight and ready for start-up and system charging. The inspection ensures that field piping is properly installed to promote oil return to the compressor.

Caution: Improperly installed piping may result in improper operation and possible damage to the cooling unit or surrounding equipment.

Ensure that the:

Fans are turning freely and that the blades are not distorted or bent.

Condensate drain line is at least the size of the drain connection.

Mechanical connections are tight, including compressor and receiver connections.

Ceiling tile adapter is secured to the building structure with properly-sized safety wire.

Covers and guards are in place.

4

InRow SC Operation

Image 10
Contents Operation 동봉된 CD 안에 한국어 매뉴얼이 있습니다 Contents Network Management Card Maintenance American Power Conversion Legal Disclaimer General Information Symbols used in this manual Cross-reference symbol used in this manual OverviewSafety Commissioning Inspection ChecklistsInitial inspection checklist Ensure thatElectrical inspection checklist Mechanical inspection checklistFinal inspection checklist User interface inspection checklistStart-up inspection checklist While the cooling unit is operating, ensure thatOperation Display InterfaceStatus Screen Name Status Information Displayed Using the Display InterfaceScrolling status screens Main menu screensNavigating the main menu Navigating the sub-menusUsing the Path statement Password entryStart the cooling unit Stop the cooling unitGeneral Configuration Cooling unit configurationView the state of input and output contacts ContactsEdit the normal state of input and output contacts Cooling Group Configuration Configure the cooling groupConfigure Modbus Identify the cooling unitSetpoints Control the EnvironmentSupply Air Run hours ThresholdsService intervals Password & time-out Display SettingsDate and time Configure display Display unitsNetwork Configuration Configure networkView Status Readings Cooling unit statusAbout the cooling unit Cooling group statusModel Respond to Alarms Event LogAlarm messages and suggested actions Displayed Alarm Message Severity Action RequiredThreshlds screen Configure Unit Discrete I/O screen. See page 17 for more Network Management Card Quick ConfigurationTCP/IP configuration methods OverviewBootp & Dhcp configuration APC Device IP Configuration WizardIni file utility NetworkTCP/IPBoot ModeDHCP onlyAdvancedDHCP Cookie Is Local access to the control console Remote access to the control consoleControl console Choose Network from the Control Console menuAccess a Configured Network Management Card Web interfaceTelnet and SSH Simple Network Management Protocol Snmp ModbusRecover From a Lost Password Cleanliness MaintenanceMonthly Preventive Maintenance EnvironmentMechanical ElectricalQuarterly Preventive Maintenance Functional testsSemi-Annual Preventive Maintenance Troubleshooting Problem Possible Cause Corrective ActionProblem Possible Cause Terms of warranty WarrantyOne-Year Factory Warranty Non-transferable warranty ExclusionsWarranty claims Page Page 990-2684A-001 2009