Follow the following procedure to vent through the roof:

1.Cut the necessary holes through the roof and ceiling

2.Install the exhaust vent and air intake plastic pipes as shown in Figure 17. Make sure that the installation meets the local codes and/or The National Fuel Gas Code ANSI Z223.1 (Latest Edition) or CGA/CAN B149 Installation Code.

Figure 17. Typical Vertical Power Vent System Installation

Through The Wall Venting With Low Ground Clearance:

When venting cannot exit through the wall at a height greater than or equal to 12” (30.5 cm) (and above expected snow level) from the ground, then the installation must be modified as shown below (see Figure 18). Refer to Tables 3 or 4 for maximum venting lengths using 3” (7.6 cm) or 4” (10.2 cm) diameter plastic pipe.

26

Image 26
Contents With Troubleshooting Guide What to do if YOU Smell GASTable of Contents Page If YOU Smell GAS Do not Operate the Appliance Until the Leakage is CorrectedSpecifications SectionFeatures Section III General InformationTemperature and Pressure Relief Valve Dishwashing Machine Requirements Condensate Elbow With LoopSection IV Installation Instructions Unpacking Minimum Clearance To CombustibleAIR Requ Rements LocationRemove Crate Confined Space Mechanical Exhausting of Room AIRUnconfined Space Chemical Vapor CorrosionTypical Installation Illustration Typical Front Inlet ConnectionTypical Two Water Heater Connection Section V Water Connections Instructions for ConnectionsApproximate TIME/TEMPERATURE Relationships in Scalds ScaldingAlternate Space Heating Water Connections Alternate Space Heating ConnectionsTypical Plumbing Schematic for Zoned Heating Section VI VentingDirect Vent Installation VentingExceptions for Installations Page Typical Horizontal Direct Vent System Typical Vertical Direct Vent System Installation Power Vent Installation Direct Vent Maximum Vent LengthTypical Horizontal Power Vent System Typical Vertical Power Vent System Installation Power Vent Maximum Vent Length Coaxial Venting Installation ProcedureDimensional Layout of Concentric Vent Kit Concentric Vent Roof Top Attachment Vent Pipe Preparation Initial PreparationSection VII GAS Connections Selection of MaterialsGAS Meter Size Natural Gases only GAS Pressure RegulationWiring Diagram and Schematic Section Viii Electrical ConnectionsTo Fill the Water Heater Section IX Operating InstructionsGeneral Instructions Sequence of OperationTemperature Adjustm NT Lighting InstructionsBurner Flame Check Sight Glass LocationGeneral Section X MaintenanceMaintenance Schedule Filling Water Heater Flushing Water HeaterDraining Water Heater Sediment and Lime Scale RemovalRelief Valve Anode Inspection and ReplacementDrain Valve and Tank Access Panel Vent and AIR Intake System Combustion System InspectionSection XI Troubleshooting Guide ReferenceIs there continuity across the Hot Surface Ignitor? If Section XI Parts List EF Series Water HeaterCombustion Surround Assy CC Ignition Control Assy