A.O. Smith BTF-75 warranty Primer, Cement, Making the Joint, Step a, Step B, Stepe, Step F

Page 11

Rag - Cotton (Not Synthetic)

Primer and Cleaner

Solvent Cement - PVC for PVC Components and CPVC for CPVC Components

Containers - Metal or Glass to hold Primer and Cement. Select the type of PVC or CPVC materials to be used on the basis of their application with respect to chemical resistance, pressure rating, temperature characteristics,etc.

Insertion Tool - Helpful for larger diameter pipe and fittings (6" and above).

PRIMER

It is recommended that Tetrahydrofuran (THF) be used to prepare the surfaces of pipe and fittings for solvent welding. Do not use water, rags, gasoline or any other substitutes for cleaning PVC or CPVC Surfaces. A chemical cleaner such as MEK may be used.

CEMENT

The cement should be a bodied cement of approximately 500 to 1600 centipoise viscosity containing 10-20% (by weight) virgin PVC material solvated with tetrahydrofuran (THF). Small quantities of dimethyl formamide (DMF) may be included to act as a retarding agent to extend curing time. Select the proper cement; Schedule 40 cement should be used for Schedule 40 pipe. Never use all-purpose cements, commercial glues and adhesives or ABS cement to join PVC or CPVC pipe and fittings.

SAFETY PRECAUTION: PRIMERS AND CEMENTS ARE EXTREMELY FLAMMABLE, AND MUST NOT BE STORED OR USED NEAR HEAT OR OPEN FLAME. ALSO, USE ONLY IN A WELL-VENTILATED AREA.

3.MAKING THE JOINT

A. Cutting

Pipe must be squarely cut to allow for the proper interfacing of the pipe end and the fitting socket bottom. This can be accomplished with a miter box saw or wheel type cutter. Wheel type cutters are not generally recommended for larger diameters since they tend to flare the corner of the pipe end. If this type of cutter is used, the flare on the end must be completely removed.

NOTE: Power saws should be specifically designed to cut plastic pipe.

STEP A

B. Deburring

Use a knife, plastic pipe deburring tool, or file to remove burrs from the end of small diameter pipe. Be sure to remove all burrs from around the inside as well as the outside of the pipe. A slight chamfer (bevel) of about 10°-15° should be added to the end to permit easier insertion of the pipe into the end of the fitting. Failure to chamfer the edge of the pipe may remove cement from the fitting socket, causing the joint to leak.

STEP B

C. Test dry fit of the joint

Tapered fitting sockets are designed so that an interference fit should occur when the pipe is inserted about 1/3 to 2/3 of the way into the socket. Occasionally, when pipe fitting dimensions are at the tolerance extremes, it will be possible to fully insert dry pipe to the bottom of the fitting socket. When this happens, a sufficient quantity of cement must be applied to the joint to fill the gap between the pipe and fitting. The gap must be filled to obtain a strong, leak-free joint.

D. Inspection, cleaning, priming

Visually inspect the inside of the pipe and fitting sockets and remove all dirt, grease or moisture with a clean dry rag. If wiping fails to clean the surfaces, a chemical cleaner must be used. Check for possible damage such as splits or cracks and replace if necessary.

Depth-of-entry mark

Marking the depth of entry is a way to check if the pipe has reached the bottom of the fitting socket in step F. Measure the fitting depth and mark this distance on the pipe O.D. You may want to add several inches to the distance and make a second mark as the primer and cement will most likely destroy your first one.

Apply primer to the surface of the pipe and fitting socket with a natural bristle brush (see chart). This process softens and prepares the PVC or CPVC for the solvent cementing step. Move quickly and without hesitation to the cementing procedure while the surfaces are still wet with primer.

E. Application of solvent cement

Apply the solvent cement evenly and quickly around the outside of the pipe at a width a little greater than the depth of the fitting socket.

Apply a light coat of cement evenly around the inside of the fitting socket. Avoid puddling.

Apply a second coat of cement to the pipe end.

STEPE

NOTE: Cans of cement and primer should be closed at all times when not in use to prevent evaporation of chemicals and hardening of cement. They are also very flammable and should be kept away from heat or flame.

F. Joint assembly

Working quickly, insert the pipe into the fitting socket bottom and give the pipe or fitting a 1/4" turn to evenly distribute the cement. Do not continue to rotate the pipe after it has hit the bottom of the fitting socket. A good joint will have sufficient cement to make a bead all the way around the outside of the fitting hub. The fitting will have a tendency to slide back while the cement is still wet so hold the joint together for about 15 seconds.

STEP F

11

Image 11
Contents SmartValve is a Registered Trademark of Honeywell Inc Commercial GAS, GLASS-LINED, TANK-TYPE Water HeaterForeword ROUGH-IN-DIMENSIONSALL Dimensions in Inches Recovery CapacitiesGeneral Safety Information Table of ContentsInstallation Water Connections AIR RequirementsUnconfined Space Confined SpaceVent Pipe Termination Single TemperatureClosed Water System Venting Relief ValveNumber Maximum Elbows Pipe Feet If using 3 inch vent pipeIf using 4 inch vent pipe Planning the Vent SystemPreparation of Blower Assembly Installation of Sidewall Vent SystemVent Terminal INSTALLATION, Sidewall Power Vent Wiring Schematic Figure Initial Preparation Installation of Vent SYSTEM, SidewallInstallation of Vertical Vent System Vent Pipe PreparationStep a PrimerCement Making the JointTo Operate the Heater OperationGAS Connections Connection of GAS PipeDo not TRY to Light the Burner by Hand WatertemperatureadjustmentDo not TRY to Light the Burner by Hand What to do if YOU Smell GASPurging MaintenanceTemperature Regulation Water Temperature Adjusting DialValve High Temperature CUT-OFF SwitchPower Venter Maintenance Venting SystemCathodic PROTECTION-ANODE Service and RepairTrouble Shooting CondensationYellow Flame TroubleshootingVent Pipe TOO HOT Above 170 FFlash Troubleshooting with the LEDOFF Replace HSI Check for Proper Voltage ATYES Turn on GAS Supply PlugALL Other Parts Service and Repair ExpensesClaim Procedure Tank