FULL SIZE GAS CONVECTION OVENS - REMOVAL AND REPLACEMENT OF PARTS
2. Remove the door switch lever.
8.Reverse procedure to install door assembly and check for proper adjustment as outlined under DOOR ADJUSTMENT and DOOR SWITCH ADJUSTMENT in SERVICE PROCEDURES AND ADJUSTMENTS.
OVEN DOORS
(SIMULTANEOUS DOORS)
Assembly Removal
3.Remove the lower door seal strip to expose the mounting screws of the door assembly.
4.Remove the two (2) lower sill bolts by the lower door shaft and the four (4)
NOTE: The door assembly is heavy and will drop down once the last screw is removed. If removing door assembly
5.Tilt the top of the door slightly forward and lift the door up until the bottom of the door shaft clears the opening in the sill.
6.Lay the door flat to prevent damage.
7.The top and bottom bearings are now accessible for inspection and/or replacement if needed.
A.If bearings are ok, proceed to step 8.
B.If replacing the top bearing, remove the top bearing retainer and top bearing.
C.If replacing the bottom bearing, remove it from the door shaft or the lower sill opening.
WARNING: DISCONNECT THE
ELECTRICAL POWER TO THE
MACHINE AND FOLLOW LOCKOUT /
TAGOUT PROCEDURES.
1.Remove the top front cover and bottom front cover as outlined under COVERS AND PANELS.
2.Remove the door switch lever.
3.Remove the top bearing retainers and top bearings.
4.Remove the lower door seal strip to expose the mounting screws of the door assembly.
A.Remove the two (2) lower sill bolts by the lower door shaft and the four (4)