G. Final Checklist

1)Is the icemaker level?

2)Is the icemaker in a site where the ambient temperature is within +45°F to +100°F (+7° C to +38°C) and the water temperature within +45°F to +90°F (+7°C to +32°C) all year around?

3)Is there at least 2” (5 cm) clearance at the right side for proper air circulation and at least 0.6” (15 mm) clearance at top for ease of maintenance and/or service?

4)Have all shipping carton, tape(s) and packing been removed from the icemaker? Is the cube guide in its correct position?

5)Are all components, fasteners and screws securely in place?

6)Have all electrical and piping connections been made?

7)Has the power supply voltage been checked or tested against the nameplate rating? And has a proper ground been installed in the icemaker?

8)Are the water supply line Shut-off Valve and Drain Valve installed? Has the water supply pressure been checked to ensure a minimum of 10 PSIG (0.7 bar) and a maximum of 113 PSIG (7.5 bar)?

Note: The icemaker may stop running when the water supply is OFF, or if the pressure is below 10 PSIG (0.7 bar). When the proper water pressure is reached, the icemaker automatically starts running again.

9)Have the Compressor hold-down bolts and all refrigerant lines been checked against vibration and possible failure?

10)Has the bin control operation been verified?

11)Has the end user been given the Instruction Manual and instructed on how to operate the icemaker and the importance of the recommended periodic maintenance?

12)Has the end user been given the name and telephone number of an authorized service agent?

13)Has the warranty card been filled out and forwarded to the factory for warranty registration?

12

Image 15
Contents KM-201BAH KM-260BAH KM-201BWH KM-260BWH Hoshizaki AMERICA, INC Contents KM-260BWH Specifications Nameplate RatingKM-201BAH Dimensions/ConnectionsKM-260BAH KM-201BWH KM-260BWH How to Remove Panels See Fig Location Electrical Connection Set UpWater Supply and Drain Connections See Figs KM-201BAH KM-201BWH KM-260BWH Final Checklist Startup III. Cleaning and Maintenance Instructions CleaningCleaning Procedure Thumbscrew Bracket L Evaporator Cube Guide Water Tank Sanitizing Procedure Following Cleaning Procedure Maintenance Exterior PanelsStorage Bin and Scoop Remove the water from the potable water supply line Preparing the Icemaker for Long StorageAir Filter CondenserDrain the potable Water Tank