VHX SERIES STEAMERS - REMOVAL AND REPLACEMENT OF PARTS

HEAT EXCHANGER

WARNING: SHUT OFF THE GAS BEFORE SERVICING THE UNIT.

WARNING: ALL GAS JOINTS DISTURBED DURING SERVICING MUST BE CHECKED FOR LEAKS. CHECK WITH A SOAP AND WATER SOLUTION (BUBBLES). DO NOT USE AN OPEN FLAME.

1.Blowdown the boiler and, if necessary, allow to cool.

2.Disconnect the electrical power to the machine at the main circuit box. Place a tag on the circuit box indicating the circuit is being serviced.

3.Remove the pressure gauge tubing and power cable from the rear of the control panel then remove the panel.

4.Disconnect the electrical lead wires exiting the boiler control box from:

A.Auxiliary LLCO probe (Orange).

B.Burner ground (green).

C.Air pressure switch (yellow & yellow/white stripe).

D.Main gas valve (purple & grey).

E.Pilot burner valve (red & grey).

F.Spark ignition cable.

5.Remove bolts securing the boiler control box (front) to the base frame.

A.Lift up on left side of box and slide out.

6.Disconnect pilot gas tubing from the air pressure switch tee.

7.Separate the union above the main gas valve and remove the gas valve piping assembly.

NOTE: Removal of the gas valve piping assembly assumes the use of a gas line quick connect or union at the gas supply inlet to the steamer.

8.Remove the four nuts from combustion blower mounting flange and remove blower from burner tube assembly.

9.Remove the four bolts connecting the horizontal flue (left of boiler) to the flue "transition" piece.

A.Separate the horizontal flue from flue "transition" piece, leaving the horizontal flue in place.

10.Remove the four nuts from the complete burner tube assembly then slowly pull the assembly straight out from the heat exchanger.

CAUTION: Use care while removing as to not damage the ceramic insulation surrounding the burner.

11.Remove the flue "transition" piece from the heat exchanger.

Page 19 of 68

 

F24700 (October 2001)

 

Image 19
Contents VHX24G Shown VHX Boiler Base Series High Efficiency GAS SteamersTable of Contents VHX Series Steamers Maintenance Cleaning Introduction InstallationGeneral Boiler Control Styles Electrical Water Conditioning SpecificationsSystem Water SupplySpecial ToolsGas Supply StandardVHX Series Steamers Operation Steamer OperationCabinet Base Boiler Cooking Compartment ControlsBoiler Blowdown Steamer Shut OFF Ignition Control Module Component FunctionVHX Series Steamers Component Function Blowdown/DrainPressure Relief Valve Steam Header AssemblyWater Level Water Inlet Valve manualSteam Supply Manifold Compartment Pressure SwitchSteam Solenoid Valve Manifold Pressure GaugeCabinet Base Boiler Controls Removal and Replacement of PartsVHX Series Steamers Removal and Replacement of Parts Component LocationsCabinet Base Boiler Controls Relay Board Water Level Controls Main or Auxiliary LlcoCooking Compartment Controls Pressure Switches Water Level Gauge AssemblyBoiler Assembly Boiler Fill and Cold Water Condenser Solenoid Valves Pilot GAS Valve Main GAS ValveComplete Burner Assembly Burner Head AssemblyHeat Exchanger VHX Series Steamers Removal and Replacement of Parts Removal Cooking Compartment DoorsGasket Handle Latch AssemblyInspection Service Procedures and AdjustmentsClean-Out BoilerDescaler Cathodic Protector Water Level Probe Housing BlowdownTest Water Level ControlsAuxiliary Low level Cut-Off Control Cycling High LimitSmall increments Fill and Cold Water Solenoid ValvesBoiler BLOWDOWN/DRAIN Solenoid Valve Inline Water Strainer CleaningMain Burner Ignition Checks Pressure Switch AdjustmentGAS Manifold Pressure Adjustment VHX Series Steamer Service Procedures and Adjustments AIR Pressure Switch Adjustment GAS Pilot Pressure Adjustment Pressure Readings Inches W.C GAS Manifold Pressure Adjustment Terminals Ignition Control Module ChecksSpark Verification Test Cooking Compartment Doors Intake Shut-Off Valve Adjustment Steam FlowDoor Sealing Adjustment Cooking CompartmentVHX Series Steamer Electrical Operation Door Latch AdjustmentLow Level Cut-Off & Differential Control Electrical OperationAuxiliary Low Level Cut-Off LED Legend Board Layout and LED LegendAux Water Level Satisfied State B Boiler Operational Status LED IndicatorReset Engaged State C Initial Conditions State aBurner ON, Boiler Heating to generate steam State E Air Pressure Switch Satisfied State DK32 Close K51 CloseHL-LED Sequence of OperationNEW Style Controls Boiler Initial Fill and PreheatN14, N16, N17 go out N9, N10, N11, N12, N13 go outBoiler Blowdown/drain Water Refill After Initial FillVHX Series Steamer Electrical Operation Cooking Compartment Controls This page Intentionally Left Blank Models Built After 5/25/00 New Style Boiler Controls SchematicsVHX Series Steamer Electrical Operation Models Built Before 5/25/00 Old Style Boiler Controls Cooking Compartment Controls Wiring Diagrams VHX Series Steamer Electrical Operation Models Built Before 5/25/00 Old Style Boiler Controls VHX Series Steamer Electrical Operation Cooking Compartment Controls VHX Series Steamer Troubleshooting TroubleshootingBoiler Base Controls Symptom Possible Causes Adjustments Boiler blowdown solenoid valve clogged and not fully closing Boiler Base Procedures and Adjustments VHX Series Steamer VHX Series Steamer Condensed Spare Parts List Condensed Spare Parts ListNEW Style Controls only VHX24G, VHX24G5, MHB24G