VHX SERIES STEAMER - ELECTRICAL OPERATION

Door Latch Adjustment

Should the cooker door jam and can not be opened, DO NOT FORCE OR PRY the door as damage will occur.

First, try lifting up on the bottom of the door at the handle end to disengage the latch. If that does not work, remove the right side panel.

The striker that catches on the door latch is located behind the front face of the cooking cavity. Remove the nut from the striker and this will release it from the panel.

Once the nut and washer have been removed, door will open freely.

Remove any burrs on the striker that may cause the latch to stick. Reinstall the striker and adjust, so door will not jam.

To adjust:

1.Reinstall the striker with the slot pointing upwards and hand tighten nut only.

2.Close the door to center the striker in the oval mounting hole.

3.Open the door and check the strikers’ slot for horizontal alignment. The slot on the striker must be kept horizontal in order for the door latch to catch it properly and latch.

4.Once the proper slot alignment has been set, hold the striker close to its base using a rag and vise grips, then tighten the striker nut. Be careful not to damage the striker slot when tightening or door may not latch properly.

NOTE: Do not over tighten as the striker will begin to turn and change alignment.

F24700 (October 2001)

 

Page 40 of 68

 

Image 40
Contents VHX Boiler Base Series High Efficiency GAS Steamers VHX24G ShownTable of Contents VHX Series Steamers Maintenance Cleaning Introduction InstallationGeneral Boiler Control Styles Water Conditioning Specifications SystemWater Supply ElectricalTools Gas SupplyStandard SpecialSteamer Operation Cabinet Base BoilerCooking Compartment Controls VHX Series Steamers OperationBoiler Blowdown Steamer Shut OFF Component Function VHX Series Steamers Component FunctionBlowdown/Drain Ignition Control ModuleSteam Header Assembly Water LevelWater Inlet Valve manual Pressure Relief ValveCompartment Pressure Switch Steam Solenoid ValveManifold Pressure Gauge Steam Supply ManifoldRemoval and Replacement of Parts VHX Series Steamers Removal and Replacement of PartsComponent Locations Cabinet Base Boiler ControlsCabinet Base Boiler Controls Relay Board Water Level Controls Main or Auxiliary LlcoCooking Compartment Controls Pressure Switches Water Level Gauge AssemblyBoiler Assembly Pilot GAS Valve Main GAS Valve Boiler Fill and Cold Water Condenser Solenoid ValvesBurner Head Assembly Complete Burner AssemblyHeat Exchanger VHX Series Steamers Removal and Replacement of Parts Removal Cooking Compartment DoorsGasket Latch Assembly HandleService Procedures and Adjustments Clean-OutBoiler InspectionWater Level Probe Housing Blowdown Descaler Cathodic ProtectorWater Level Controls TestAuxiliary Low level Cut-Off Control High Limit CyclingFill and Cold Water Solenoid Valves Small incrementsInline Water Strainer Cleaning Boiler BLOWDOWN/DRAIN Solenoid ValvePressure Switch Adjustment Main Burner Ignition ChecksGAS Manifold Pressure Adjustment VHX Series Steamer Service Procedures and Adjustments AIR Pressure Switch Adjustment GAS Pilot Pressure Adjustment Pressure Readings Inches W.C GAS Manifold Pressure Adjustment Ignition Control Module Checks TerminalsSpark Verification Test Intake Shut-Off Valve Adjustment Steam Flow Door Sealing AdjustmentCooking Compartment Cooking Compartment DoorsDoor Latch Adjustment VHX Series Steamer Electrical OperationElectrical Operation Low Level Cut-Off & Differential ControlAuxiliary Low Level Cut-Off Board Layout and LED Legend LED LegendBoiler Operational Status LED Indicator Reset Engaged State CInitial Conditions State a Aux Water Level Satisfied State BAir Pressure Switch Satisfied State D K32 CloseK51 Close Burner ON, Boiler Heating to generate steam State ESequence of Operation NEW Style Controls BoilerInitial Fill and Preheat HL-LEDN9, N10, N11, N12, N13 go out N14, N16, N17 go outWater Refill After Initial Fill Boiler Blowdown/drainVHX Series Steamer Electrical Operation Cooking Compartment Controls This page Intentionally Left Blank Schematics Models Built After 5/25/00 New Style Boiler ControlsVHX Series Steamer Electrical Operation Models Built Before 5/25/00 Old Style Boiler Controls Cooking Compartment Controls Wiring Diagrams VHX Series Steamer Electrical Operation Models Built Before 5/25/00 Old Style Boiler Controls VHX Series Steamer Electrical Operation Cooking Compartment Controls VHX Series Steamer Troubleshooting TroubleshootingBoiler Base Controls Symptom Possible Causes Adjustments Boiler blowdown solenoid valve clogged and not fully closing Boiler Base Procedures and Adjustments VHX Series Steamer VHX Series Steamer Condensed Spare Parts List Condensed Spare Parts ListNEW Style Controls only VHX24G, VHX24G5, MHB24G