VHX SERIES STEAMER - TROUBLESHOOTING
SYMPTOM |
| POSSIBLE CAUSES |
|
|
|
Boiler Slow to Pressurize | 1. | Low water supply pressure, inline water strainer clogged or fill |
(over 15 min. to achieve operating |
| solenoid valve malfunction. See "INLINE WATER STRAINER |
pressure) |
| CLEANING" and "FILL AND COLD WATER SOLENOID |
|
| VALVES" in "SERVICE PROCEDURES AND |
|
| ADJUSTMENTS". |
| 2. | Boiler blowdown solenoid valve clogged and not fully closing. |
|
| Check for a slow leak out of steamer drain. If not able to verify, |
|
| then proceed to step 3. If blowdown solenoid valve appears to |
|
| be functioning properly, then proceed to step 4. |
| 3. | Turn power switch OFF, disconnect lead wires from blowdown |
|
| solenoid and remove it for inspection. |
| 4. | A heavy |
|
| boiler, creating an insulating effect. Examine interior of boiler |
|
| as outlined under “BOILER” in "SERVICE PROCEDURES AND |
|
| ADJUSTMENTS". |
| 5. | Low incoming gas pressure is reducing BTU output. |
|
| A. Verify gas supply line to the steamer is a minimum of one |
|
| inch diameter (ID). |
|
| B. Check incoming line and manifold gas pressures as |
|
| outlined in "GAS MANIFOLD PRESSURE ADJUSTMENT" |
|
| under "SERVICE PROCEDURES AND ADJUSTMENTS". |
| 6. | Gas valve malfunction. |
|
| A. Check incoming line and manifold gas pressures as |
|
| outlined in "GAS MANIFOLD PRESSURE ADJUSTMENT |
|
| under "SERVICE PROCEDURES AND ADJUSTMENTS". |
|
|
|
Boiler will not heat or build pressure. | 1. | Gas not on. |
| 2. | Power/reset switch assembly malfunction. |
| 3. | Boiler not filling - check fill solenoid for power, clogging or |
|
| malfunction. |
| 4. | Gas pilot and/or gas manifold pressure low. See "GAS PILOT |
|
| PRESSURE ADJUSTMENT" and "GAS MANIFOLD |
|
| PRESSURE ADJUSTMENT" in "SERVICE PROCEDURES |
|
| AND ADJUSTMENTS". |
| 5. | Cycling pressure switch open or set too high. Steamer is |
|
| cycling on high limit. |
| 6. | High limit pressure switch open and not |
|
| (malfunction). |
| 7. | Water too "pure" for probes to properly conduct electricity. |
|
| NOTE: Items 8 & 9 see "WATER LEVEL CONTROLS TEST" |
|
| in "SERVICE PROCEDURES AND ADJUSTMENTS". |
| 8. | Water Level Control malfunction. |
| 9. | Aux. Water Level Control malfunction. |
|
|
|
Pressure relief valve(s) opening or | 1. | Pressure overshoot on initial startup or long burner on times |
leaking. |
| under heavy usage. |
| 2. | Pressure relief valve malfunction. |
| 3. | Cycling pressure switch set to high. |
| 4. | High limit pressure switch not set correctly or malfunctioning. |
|
|
|
F24700 (October 2001) |
| Page 64 of 68 |
|