U-Line CLR2060 manual Assembling the Door

Page 10

CLR2060 — Clear Ice Maker

 

 

 

Back of

Tape

Removed

Wood

Door Panel

Panel

 

Side of

 

Wood Panel

Bottom of

 

Wood Panel

5/16"

3/8"

Bottom

Both Sides

Figure 20

 

Typical

Door Panel

Wood Panel

 

Top

Pivot Plate

#10 x 5/8"

Round Head Screw

Six Required

Plastic Spacer

Six Required

Figure 22

5.Remove the existing bottom pivot plate and replace with the Full Overlay pivot plate (see Figure 23).

1"± 1/32"

Figure 21

Rear View

of

Wood Panel

1"± 1/32"

Drill 5/32" x 3/8" Deep for use with #10 x 5/8" Wood Screw and Nylon Spacer – 6 Places

27"± 1/4"

14-5/16"±1/4"

1"± 1/8"

Existing

 

Door

Wood Panel Bottom Pivot Plate

 

(5/8" Longer Than

Existing Bottom Pivot Plate

Existing Bottom Pivot Plate,

(Remove and Discard)

Flush Side Facing Out)

 

#8-32 x 3/8" SEMS Hex Screw

 

Two Places

Figure 23

IMPORTANT

Door panel and overlay panel must be aligned properly or the door will not operate correctly.

Assembling the Door

1.Install the assembled panel by sliding the original door panel back into the doorframe.

2.Replace the two-piece Modified Handle assembly and secure with the two screws removed in Step 5 under Removing Existing Door.

3.Starting at the corners and working toward the center, push the door gasket back into place.

4.Attach the door panel to the overlay panel using #10 x 5/8" wood screws and nylon spacers. The nylon spacers fit between the overlay panel and the door panel as shown in Figure 22. The spacers allow the original door panel to slide back into the 1/4"-thick door reveal (channel).

Installing the Door

1.Remove the existing hinges from the unit, saving the door closure assembly.

2.Install the new Replacement Top Hinge onto the unit (see Figure 24).

www.U-LineService.com

10

02/2005

Image 10
Contents CLR2060 Clear Ice Maker Contents Follow Safety PrecautionsTools/Materials Required General PrecautionsInspect and Plan InspectionDoor Swing/Clearances Information Product DimensionsCut-Out Dimensions Prepare SiteReversing the Door Side-By-Side Installation Instructions Other Site Requirements Custom 1/4 Door Panel Insert Prepare and Install Door Panel Door Panel Installation Door Panel PreparationFull Overlay Door Panel Installation Instructions Attaching the Full Overlay PanelAssembling the Door Adjust Door Adjusting Door AlignmentChecking Door Alignment Prepare Plumbing Drain ConnectionGravity Drain Factory-Installed Drain Pump Locally-Installed Drain Pump Go on to 7 Prepare Power Supply Water Supply ConnectionPrepare Power Supply Level the Unit Electrical SpecificationsLeveling Information Installation Tip Installation of the CLR2060Install the Unit Initial Start-Up Installation TroubleshootingStart-Up for the First Time Start-Up Troubleshooting About SettingsService Information Who to Call