Step 4

Step 5

Step 6

Step 7

Step 8

Step 9

Turn the AZIMUTH EAST/WEST switch to either position and while the antenna is rotat- ing, carefully use a clamp on ammeter in accordance with the ammeter manufacturer’s instructions to take current readings off each of the three conductors (phases) connect- ed to the load side of the azimuth drive motor circuit breaker. Record the current draw in the equipment log and compare the readings to the reference values entered in the installation/acceptance check off. If the readings differ by more than five percent, refer to appropriate troubleshooting information and perform applicable corrective action. Then take voltage readings off each of the three conductors; the readings should agree with each other—within two percent. Turn the AZIMUTH switch to OFF.

Repeat steps (5) with the AZIMUTH EAST/WEST switch in the alternate operating posi- tion.

Turn the ELEVATION DOWN/UP switch to either position and while the antenna is rotat- ing, carefully use a clamp on ammeter in accordance with the ammeter manufacturer’s instructions to take current readings off each of the three conductors (phases) connect- ed to the load side of the elevation drive motor circuit breaker. Record the current draw in the equipment log and compare the readings to the reference values entered in the installation/acceptance check off. If the readings differ by more than five percent, refer to appropriate troubleshooting information and perform applicable corrective action. Then take voltage readings off each of the three conductors; the readings should agree with each other within two percent. Turn the ELEVATION switch to OFF.

Repeat steps (7) with the ELEVATION DOWN/UP switch in the alternate operating posi- tion.

If all voltage and current readings are within tolerance, close the local control/motor drive controller inner door and place the LOCAL/REMOTE switch in the REMOTE posi- tion to return antenna control to the studio. Then close and lock the outer local control/motor drive controller door.

When preserving the component parts, refer to the following paragraphs in this section.

49

Preventive Maintenance

Image 49
Contents Meter ESA Table of Contents Introduction Meter Earth Station AntennaProprietary Data Information and Assistance Technical Customer Service CenterHow to Use This Manual Overview ContentGetting Started OverviewTool Size Quantity Recommended ToolsGetting Started Returning Equipment Step Overview Foundation Preparation Installation Procedures1b A-325 Tensioning For bolts over four diameters Tensioning StepTripod Ground Mount Assembly Azimuth Beam Step Support Legs Assembly Step Step Step Panning Frame Assembly Step Step Step Step Step Step Step Elevation Jackscrew Assembly Step Step Azimuth Jackscrew Assembly Step Mount Assembly Step Step Step Step 22193/223180 Installation Procedures Installation Procedures Installation Procedures Installation Procedures Installation Procedures Installation Procedures Installation Procedures Installation Procedures Installation Procedures Operation Overview Acquiring a SatelliteStep Polarization at 45 degrees from Optimum Setting Maximizing Odd Transponders Subreflector Adjustment Preventive Maintenance Overview General Cleaning Electrical PartsPreventive Maintenance Antenna Preventive Maintenance Drive System Voltage Current Checks Step Step Preventive Maintenance Jackscrews/Motors Gear Motor/Housing Fill Drain Requirements Lubrication Chart High-Speed Antenna Lubrication Points Medium-Speed Antenna Lubrication Points