Andrew 3.7-Meter Earth Station Antenna manual Drive System Voltage Current Checks Step

Page 82

Drive System

Voltage and

Current Checks

Step 1

Step 2

Step 3

Check security of antenna mounting and interconnecting assembly hardware. Be cer-

tain all electrical grounding connections (including cross-axis grounding straps) are intact and secure, not corroded or broken. Thoroughly clean any noticeable corroded portions of grounding cables, unplated portion of universal terminals and corresponding mounting surfaces using a wire brush. Replace rather than tighten any loose A-325 structural hardware. The hardware distorts at initial installation and once loosened will not maintain the required high strength friction connection. All other assembly and instal- lation hardware should be tightened to its original torqued condition. When installing new structural hardware, do not use a wrench with a lever arm longer than two feet.

Examine painted aluminum and galvanized surfaces and tough-up where required.

At the conclusion of the installation procedure prior to turning the system over to the sta- tion facility, an installation acceptance check off sheet was prepared and duly signed off if installed by Andrew crew. Part of this check off included voltage readings retaken to determine if proper voltage was available. Current readings were also taken as a refer- ence for future comparison to serve as a troubleshooting aid in determining possible equipment degradation and shortened life. Any current reading taken during the follow- ing procedure that varies by more than five percent from the pre-established reference values necessitates troubleshooting the particular system involved to determine the cause and required corrective action.

Approximately every three months and during a period of down time, disconnect as applicable the RF transmitter and all power supplies. The main disconnect switch in the main load center box at the antenna site must be in the ON position and the LOCAL/REMOTE switch in the local control motor drive controller must be in the LOCAL position.

Open the outer local control/motor drive controller door at the antenna site to gain access to the conductors supplying power to the azimuth, elevation, and polarization drive motors.

NOTE: During the following procedures, the antenna drives (azimuth, elevation, and polarization) will be powered to rotate the antenna and feed in both directions of travel. Check that this condition can be tolerated from a safety as well as an operational stand- point, and that the electrical limits are not reached before the testing is concluded. Reaching an electrical limit before concluding a test necessitates rotating the antenna or feed in the opposite direction a sufficient distance to permit retesting in the desired direction.

Turn the FEED CCW/OFF/CW switch to either the CW or CCW position and while the feed is rotating, carefully use a clamp on ammeter in accordance with the ammeter man- ufacturer’s instructions to take current readings off each of the three conductors (phases) connected to the load side of the polarization motor circuit breaker. Record the current draw in the equipment log and compare the readings to the reference values entered in the installation/acceptance check off. If the readings differ by more than five percent, refer to appropriate troubleshooting information and perform applicable corrective action. Then take voltage readings off each of the three conductors; the readings should agree with each other within two percent. Turn the FEED CCW/OFF/CW switch to OFF.

82

Preventive Maintenance

Image 82
Contents Meter ESA Table of Contents Meter Earth Station Antenna IntroductionCustomer Service Center Proprietary Data Information and Assistance TechnicalOverview Content How to Use This ManualOverview Getting StartedRecommended Tools Getting Started Returning Equipment Step Getting Started For Mpjk Types Only Main Reflector Assembly Enclosure Assembly Reflector-To- Mount Assembly Subreflector Feed System Installation Procedures Overview Foundation PreparationTensioning Step 1b A-325 Tensioning For bolts over four diametersMount Unpacking Assembly Using a Crane Step 4b Ground Mount Assembly Base Hardware Assembly Without a Crane Step Ground Mount Assembly Alignment with Anchor Bolts6a Manual Lift 8a Ground Mount Assembly Base Hardware Motorizable Pedestal Ground Mount Assembly Step 8b Ground Mount Assembly Tiller Arm Hardware8d Ground Mount Assembly Tiller Arm Hardware Manual Pedestal Ground Mount Assembly Step 10 Waxing BoltsStep 13 Elevation and Azimuth Struts Step 17a Azimuth Strut Assembly Front 17b Azimuth Strut Assembly Rear 20 Bracket-Support Plates Top View 21a Elevation Strut Bracket Manual Actuator Assembly Step 22a Manual Actuator Assembly23 Azimuth Pivot Bracket Assembly 25a Jack Unscrew Procedure 26 Protective Boot Attachment 28a Elevation Jack Step Embedded Pipe Ground Mount Assembly Step 29b Left Side Frame AttachmentStep Elevation/Azimuth Strut Assembly 29d Elevation/Azimuth Strut Assembly29f Elevation Axis Weldment Attachment 29g Azimuth Strut/Pointer Attachment 29i Fine Azimuth Adjustment Attachment Reflector Unpacking Step 30a Domestic Pack30b Export Pack Step Assembly 31 Reflector Seam Alignment32 Seam Bolt Insertions Very Important 33c Alignment Bolt Insertions 34a Mounting Ring Placement 35a Mounting and Center Rings -35b Mounting and Center Rings Alignment Test Step 38a Enclosure Final Assembly Enclosure Pedestal Mount Only Step39a Enclosure Hardware Step Reflector-to-Mount Assembly Using a Crane Step 43 Safety Rope Tag Lines44b Crane Lift Without a Crane Step 46 Reflector to Mount 48 Enclosure Bracket Alignment Step 50a Reflector to Mount Reflector-to-Mount Assembly Embedded Pipe Ground Mount Step 52a Subreflector Strut Assembly Subreflector Step53a Subreflector Assembly 53c Subreflector Assembly 54a Subreflector Attachment Subreflector Struts Embedded Pipe Ground Mount Assembly Step Subreflector Adjustment Step Step Step Feed System Overview Acquiring a Satellite Step OperationPure Noise Signal on Spectrum Analyzer Step Polarization at 45 degrees from Optimum Setting Maximizing Odd Transponders Operation Subreflector Adjustment Preventive Maintenance Overview General Cleaning Electrical PartsPreventive Maintenance Antenna Preventive Maintenance Drive System Voltage Current Checks Step Step Pedestal Mount Bearing Pad Adjustment Preventive Maintenance Jackscrews/Motors Gear Motor/Housing Fill Drain Requirements Service Lube Quantity Andrew