Andrew 3.7-Meter Earth Station Antenna manual Motorizable Pedestal Ground Mount Assembly Step

Page 22

Motorizable

Pedestal Ground

Mount Assembly

Step 1

Step 2

Step 3

Step 4

The ground mount assembly enables 180° positioning for selected azimuth viewing. Azimuth range coverage is ±90° divided into three 120° continuous ranges with 30° overlap. Elevation adjustment is continuous from 0 to 90°.

Position and mount 204737 azimuth tiller arm weldment to ground mount assembly as shown using 0.75 x 1.75 in. A-325 bolts and nuts. Tighten hardware per A-325 tension- ing procedure. NOTE: Mounting position of azimuth tiller arm weldment is dependent upon predetermined azimuth range requirements as shown.

Apply supplied stick lubricant to set screw threads. Loosely install 0.50 x 1.0 in. set screws in azimuth and 0.50 x 1.50 in. set screws in elevation strut supports.

Position and mount 204754 elevation support angle assembly to ground mount as shown using 0.50 x 1.75 in. A-325 bolts, flat washers and nuts. Tighten hardware per A- 325 tensioning procedure.

Loosely install supplied 0.75 x 2.00 in. A-325 bolts, flat washers and nuts in elevation support angle assembly. This hardware along with the upper elevation strut hardware will be attached to the antenna and tightened to the A-325 tensioning procedure at the time of antenna installation.

Support Plate

1/2 x 1” Bolt and

3/4” Flat Flat Washer

Washer

3/4” Threaded

Rod

Pivot Block

3/4 x 1-3/4” Bolt and Nut

Figure 3-8b: Ground Mount Assembly Tiller Arm Hardware

EL SPT Angle

Assembly

3/4 x 2” Bolt and Flat Washer (2 Washers per Bolt, one each on Reflector and Mount Side)

AZ Tiller Arm

Weldment

Figure 3-8c: Ground Mount Assembly Elevation Support Angle

22

Installation Procedures

Image 22
Contents Meter ESA Table of Contents Meter Earth Station Antenna IntroductionCustomer Service Center Proprietary Data Information and Assistance TechnicalOverview Content How to Use This ManualOverview Getting StartedRecommended Tools Getting Started Returning Equipment Step Getting Started For Mpjk Types Only Main Reflector Assembly Enclosure Assembly Reflector-To- Mount Assembly Subreflector Feed System Installation Procedures Overview Foundation PreparationTensioning Step 1b A-325 Tensioning For bolts over four diametersMount Unpacking Assembly Using a Crane Step 4b Ground Mount Assembly Base Hardware Assembly Without a Crane Step Ground Mount Assembly Alignment with Anchor Bolts6a Manual Lift 8a Ground Mount Assembly Base Hardware Motorizable Pedestal Ground Mount Assembly Step 8b Ground Mount Assembly Tiller Arm Hardware8d Ground Mount Assembly Tiller Arm Hardware Manual Pedestal Ground Mount Assembly Step 10 Waxing BoltsStep 13 Elevation and Azimuth Struts Step 17a Azimuth Strut Assembly Front 17b Azimuth Strut Assembly Rear 20 Bracket-Support Plates Top View 21a Elevation Strut Bracket Manual Actuator Assembly Step 22a Manual Actuator Assembly23 Azimuth Pivot Bracket Assembly 25a Jack Unscrew Procedure 26 Protective Boot Attachment 28a Elevation Jack Step Embedded Pipe Ground Mount Assembly Step 29b Left Side Frame AttachmentStep Elevation/Azimuth Strut Assembly 29d Elevation/Azimuth Strut Assembly29f Elevation Axis Weldment Attachment 29g Azimuth Strut/Pointer Attachment 29i Fine Azimuth Adjustment Attachment Reflector Unpacking Step 30a Domestic Pack30b Export Pack Step Assembly 31 Reflector Seam Alignment32 Seam Bolt Insertions Very Important 33c Alignment Bolt Insertions 34a Mounting Ring Placement 35a Mounting and Center Rings -35b Mounting and Center Rings Alignment Test Step 38a Enclosure Final Assembly Enclosure Pedestal Mount Only Step39a Enclosure Hardware Step Reflector-to-Mount Assembly Using a Crane Step 43 Safety Rope Tag Lines44b Crane Lift Without a Crane Step 46 Reflector to Mount 48 Enclosure Bracket Alignment Step 50a Reflector to Mount Reflector-to-Mount Assembly Embedded Pipe Ground Mount Step 52a Subreflector Strut Assembly Subreflector Step53a Subreflector Assembly 53c Subreflector Assembly 54a Subreflector Attachment Subreflector Struts Embedded Pipe Ground Mount Assembly Step Subreflector Adjustment Step Step Step Feed System Overview Acquiring a Satellite Step OperationPure Noise Signal on Spectrum Analyzer Step Polarization at 45 degrees from Optimum Setting Maximizing Odd Transponders Operation Subreflector Adjustment Preventive Maintenance Overview General Cleaning Electrical PartsPreventive Maintenance Antenna Preventive Maintenance Drive System Voltage Current Checks Step Step Pedestal Mount Bearing Pad Adjustment Preventive Maintenance Jackscrews/Motors Gear Motor/Housing Fill Drain Requirements Service Lube Quantity Andrew