1.Slide the wooden frame out of the oven.

2.Before installing the hearth core plates or steel hearth assembly, be sure that the bottom heat deflectors are properly positioned with the treaded side (bumps) in the up position.

3.If the oven is supplied with a steel hearth assembly, place the hearth spacers (with the flat side in the up position) on the extreme left and right sides of the oven resting on the heat deflectors. Making sure the hearth spacers are not disturbed, slide the steel hearth assembly into the oven.

4.If oven is supplied with hearth core plates, slide the plates into the oven.

GPD-48 is supplied with (2) two hearth core plates.

GPD-60 is supplied with (3) three hearth core plates.

5.Installation instruction for Hearth.

a.Place a screwdriver, or a similar prying device, between the core plate and hearth frame support, (being careful not to chip the core plate) then place two spacer clips (PN G03086-1-9) between the core plate and the hearth frame support. (See instructions sheet – PN 1917401) 6” from front & 6” from rear.

b.Place a screwdriver between the back of the right core plate and hearth frame support. Pry the core plate forward, away from the hearth support and place a clip within the space centered on each core plate.

c.Repeat step 2 for the left core plate

d.Repeat step 3 for the center core plate for 60” unit.

Double Deck Assembly

1 Secure legs to lower section

2.Remove stainless steel top trim strip from lower unit if not already removed.

3.Tip upper unit backward. Remove vent patch at lower rear if not if not already removed.

4.Place 1” x 4” x 65” (25mm x 100mm x 1650mm) long piece of lumber across the rear top of oven to prevent stacks from misarranging.

5.Raise the top oven section up and onto the lower oven section.

6.Carefully remove piece of lumber ensuring lower section vent collar inserts into upper section vent hole.

Gas Connection

1.The appliance must be isolated from the gas supply piping system by closing its manual shut-off valve during any pressure testing of the gas supply piping system at test pressure equal to or less that ½ psig. (3.45 kpa.).

2.The appliance and its shut off valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of ½ psig. (3.45 kpa.).

NOTE: The ovens should not be installed on the same line with space heaters, broilers or other equipment with high intermittent demand.

3.When making gas connections, uses a pipe joint compound that is resistant to the action of liquefied petroleum gases.

4.Each oven is supplied with two possible gas connection locations. One is located on the right side and the other is located on the right rear corner.

5.The right side connection is plugged with a ¾ counter sunken plug. If this connection is used, you must cap the rear connection.

6.The gas pressure regulator is part of the combination valve and is adjusted to yield a pressure of 6.0” water column for natural gas and 10” water column for propane gas.

Page 8

Part # 1844063 (08/06)

Image 8
Contents For Your Safety Important Information Keep appliance area free and clear from combustiblesTable of Contents Dimensions and Specifications GPD Series REAR&SIDE GasinletGas Connections InstallationRating Plate Installation Installation ClearancesPreparation VentilationAssembly Instructions Installing Under Ventilation CanopyInstalling with Direct Ventilation Leg InstallationAssembly Instructions Double Deck AssemblyGas Connection Slide the wooden frame out of the ovenAdjustments Gas Pressure AdjustmentsFlame & Air Mixture Adjustment Always be at handCalibration AdjustmentsBy-Pass Flame Adjustment Operation Flame DivertersBreak-In Replace dialCleaning OperationTroubleshooting Guide Problem Causes Solutions1844063 08/06 Dépannage DE Guide Nettoyage Suite FonctionnementFour Du Extérieur Minute 1 pendant enfoncé robinet le MaintenirRodage FonctionnementSuite Réglages Que s’assurer de convient il faire le de avant et De ammefl DiminuerPour Trou Le par tournevis petit unRéglages Nfi métallique lfi un utiliser froid, est four leLorsque sales brûleurs de cesorifi ou Ouverture Ou conduite la de surcharge d’une probablementSuite D’ASSEMBLAGE Instructions ’un équipé est droit coté de branchement LeSystème Être doivent ’arrêt Robinet son’ASSEMBLAGE Instructions Four Suite InstallationDirecte Ventilation Une Avec Installation Installation « section la Consulter .l’usine Sols sur installation pour Convient .mm po  deSections les Consulter .adéquat ventilation de Protecteur revêtements Retirer inoxydable’installation, concernant questions de cas En Joints à pâte la de Utiliser .commandes les ouProduit, du réparation la ou l’entretien l’utilisation InférieureSeries GPD Specifications and Dimensions ’ENTRÉE SpécificationsMatières DES Table Importantes Informations Inc Industries, Commercial Garland