Section 3 — Operation
Guardian
Before starting the generator for the first time, the installer must complete the following procedures. For
2.11.2 TRANSFER SWITCH
If this generator is used to supply power to any elec- trical system normally powered by an electric utility, the National Electrical Code requires that a transfer switch be installed. The transfer switch prevents elec- trical backfeed between two different electrical sys- tems. (For additional information, see the applicable transfer switch manual for this unit.) The transfer switch, as well as the generator and other standby components, must be properly located and mounted in strict compliance with applicable codes, standards and regulations.
2.11.3 FUEL SYSTEM
Make sure the fuel supply system to the generator (a) delivers the correct fuel at the correct pressure and
(b)is properly purged and leak tested according to code. No fuel leakage is permitted. See “Specifications” (Section 1.10) for more information.
2.11.4 GENERATOR SET LUBRICATION
Check the engine crankcase oil level before operating and add oil to the proper level – the dipstick “FULL” mark. Never operate the engine with the oil level below the dipstick “ADD” mark. See “Specifications” (Section 1.10) and “Engine Oil Recommendations” (Section 1.14).
2.11.7 ELECTRICAL SYSTEM
Make sure the generator is properly connected to an approved earth ground and/or ground rod.
Make sure the generator battery is fully charged, properly installed and interconnected, and ready for use.
Check to ensure that there are no loose electrical con- nections. Restrain any loose wires to keep them clear of any moving generator set components.
3.1USING A STANDARD “GTS”
TRANSFER SWITCH
When required, the
When a GTS type transfer switch is used, it controls automatic operation and automatic transfer as fol- lows:
•Solid state circuits in the transfer switch monitor utility power source voltage.
•When utility source voltage drops below a
•After the engine starts and when the generator AC output voltage and frequency have reached a
NOTE:
This engine is shipped from the manufacturer with
2.11.5 ENGINE COOLANT
•When the utility power source voltage is restored above a
•Following
Have the engine cooling system properly filled with the recommended coolant mixture. Check the system for leaks and other problems. See “Specifications” (Section 1.10) and “Coolant” (Section 1.15).
2.11.6 BELT TENSION
Check the engine fan belt tension and condition prior to placing the unit into service and at recommended intervals. Belt tension is correct when a force of approximately 22 pounds (10 kg), applied midway between pulleys, deflects the belt about 3/8- to 5/8- inch (10 to 16 mm).
NOTE:
If the generator is installed in conjunction with a GTS type transfer switch, refer to the applicable transfer switch manual for exact operating param- eters and timing sequences.