Warning: Use of one bus only on a dual bus panel will result in false alarms for the unused bus. Power is required on both buses on a dual bus panel for normal operation.
Caution: Connect only the input voltage wire [the wire labeled BATTERY or BATT, or labeled with the negative
Caution: Caution should be taken to not reverse the input wires to the fuse platform. Within the panel, the internal return wiring is not protected by fuses. If the wires are reversed, current will flow through the unprotected return wiring in the panel to the equipment. This condition can cause damage to the equipment in the frame in which the panel is installed and to equipment in adjacent frames
Use the following procedure to connect the input power cables to the fuse platform:
1.Obtain eight lengths of #2 AWG wire for use as the input power cables.
2.Strip back 7/8 inches of insulation from one end of each wire as shown in Figure 18.
3.Slide a
4.Terminate one end of each wire with the
5.Slide the heat shrink insulation down to the lug terminal so the barrel end of the terminal is covered.
6.Use a heat gun to apply heat to the heat shrink insulation until it tightens around the wire and barrel end of the terminal.
7.Form each input cable into the shape required for connection to the input terminals and secure to side of rack.
TERMINALHEAT SHRINK TUBING
#2 AWG
COPPER
WIRE
STRIP BACK 7/8 INCH
OF INSULATION
Figure 18.
8.Use the nuts (with captive star washers) provided to secure the input power wires to the two input power terminals as shown in Figure 19. Each input power terminal has two terminals, labeled BATT and RTN. Connect the wires to the terminals as follows:
a.Battery wires: Connect to BATT