9.3Operation of the UPS in a parallel system
The
9.3.1Start-Up
13.Make sure that all connections have been made according to the installation instructions.
14.Make sure that all loads are switched off.
15.Make sure that all “maintenance switch” manual bypass switches (no. 3, p. 27/28) on the back of each UPS are in the “Bypass” position and all mains input miniature circuit breakers (no. 2, p. 27/28) on the back of each UPS are in the “OFF” position.
16.Check the position of the central external manual bypass. This must be in the “Bypass” position, i.e. supply of the load busbar by the supplying mains.
17.Now close all isolators in the output of each UPS, i.e. connect the output of each UPS with the parallel operation busbar.
18.Now insert the
The load supply now takes place via the central i external manual bypass, and the parallel operation busbar is supplied with power via the integrated manual bypasses of each UPS. However, the parallel operation busbar and load busbar are not yet connected to each other at
this time!
57