Chapter 4: Installing and Labeling the Switches in an Equipment Rack
72
Installing the Switches in an Equipment Rack
This procedure requires the following items:
Eight bracket screws (included with the switch)
Two equipment rack brackets (included with the switch)
Flat-head screwdriver (not provided)
Cross-head screwdriver (not provided)
Four standard equipment rack screws (not provided)
Perform this procedure to install the switch in a 19-inch equipment rack,
Caution
The chassis may be heavy and awkward to lift. Allied Telesis
recommends that you get assistance when mounting the chassis in
an equipment rack. E28
1. Place the unit upside down on a level, secure surface.
Figure 21. Turning the Switch Upside Down
2. Using a flat-head screwdriver, pry the rubber feet from the bottom of
the switch.
Figure 22. Removing the Rubber Feet
3. Turn the switch over.