PROCEDURE FOR FUNCTIONAL CHECK OF REPLACEMENT
COMPONENTS _________________
Microprocessor Controller (Computer) Board _________________________________
Upon completing installation of the replacement microprocessor controller (computer) board, reestablish power to the dryer.
Start the drying cycle by pressing any of the preset cycles in letters
Verify that the applicable indicator lights on the microprocessor controller (computer) board are lit. (Refer to the illustration below.)
For Models with Johnson Direct Spark Ignition (DSI) Controller (G760) ________
Theory of Operation:
Start the drying cycle. When the gas burner ignites within the chosen trial for ignition time
of the third retry/trial
DSI module will “Lock Out” (light emitting diode [L.E.D.] diagnostic indicator flashes).
A steady L.E.D. indicator indicates normal operation.
No L.E.D. indicator indicates a power or an internal
failure has occurred.
For Models with Fenwal Controls DSI Module (128937) _______________________
Theory of Operation:
Start the drying cycle. When the gas burner ignites within the chosen trial for ignition time
An unlit red L.E.D. diagnostic indicator indicates normal operation.
A lit green L.E.D. diagnostic indicator indicates dryer controller is calling for heat and that all interlocks have been satisfied.