![](/images/new-backgrounds/1055784/5578479x1.webp)
Air Box Door Panel
Spark |
|
Sleeve | Sensing |
| |
| Lead Terminals |
Earth | Fig. 40 |
Combustion Box
Door Panel
40© Baxi Heating UK Ltd 2011
Fig. 39
Fig. 41
14.0Servicing the Boiler
14.2Annual Servicing - Inspection
WARNING: The PCB Control and Fan Assembly are 325 Vdc. Isolate system controls before access
1.Ensure that the boiler is cool.
2.Remove the facia and front door panel.
3.Release the four 1/4 turn screws securing the air box door panel and remove the panel (Fig. 39).
4.Disconnect the three leads from the terminals (Fig. 40).
5.Undo the four screws securing the combustion box door and remove the door (Fig. 41).
6.Visually check for debris/damage and clean or replace if necessary the following:
a)Burner.
b)Heat exchanger fins.
c)Fan compartment (Check also for condensate leaks).
d)Insulation.
e)Door
f)Electrodes.
g)The condensate trap.
h)The condensate pump
i)Top of heat exchanger.