RS-232485/422 CONVERTERS

RS-232485/422

Converter Plus

Figure 9. Sample Multipoint Operation.

Installation Procedure for the Multipoint Application in Figure 9

1.Set all the RS-232485/422 Converters for DCE operation (jumper XW1 in position A).

2.Connect a straight-through cable from the RS-232 port on each RS-232485/422 Converter to the RS-232 port on each of the PLCs.

3.Set all the RS-232485/422 Converters for normal operation (switch S1 in the “Normal” position).

4.After a remote station has been addressed, two-way data transmission can occur between that station and the industrial controller until the industrial controller sends a “CLEAR” command. This command causes the remote PLC to resume data logging while waiting to be addressed again. Therefore, set each RS-232485/422 Converter for full-duplex operation (jumper W8 in the “FULL” [A-B] position).

5.Connect the RS-232485/422 Converters together via a 4-wire twisted-pair cable (see Figure 7).

6.Terminate (switch S2 in the TERM position) the two RS-232485/422 Converters that have the greatest cable run between them and leave the others unterminated (switch S2 in the UNTERM position).