Bunn U3A service manual SERVICE cont, LIQUID LEVEL BOARD AND LEVEL PROBE cont

Models: U3A U3

1 42
Download 42 pages 23.98 Kb
Page 21
Image 21
LIQUID LEVEL BOARD AND LEVEL PROBE (cont.)

SERVICE (cont.)

LIQUID LEVEL BOARD AND LEVEL PROBE (cont.)

9.Reconnect the pink wire to terminal 4.

10.Remove the two #8-32 screws securing the level probe to the component bracket.

11.Gently pull the probe out of the component bracket

and inspect for corrosion. Replace if necessary.

12 Place the probe so that neither end is in contact with any metal surface of the brewer.

13.Connect the brewer to the power source. Check the voltage across terminals 1 and 3, refer to chart below. There is an approximate delay of five seconds for output to stabilize.

Model

Voltage -

Voltage -

 

Jumper

Jumper

 

Not Touching

Touching

 

Frame

Frame

120/208V &

120V

0

120/240V - 3

 

 

wire w/ground

 

 

single phase

 

 

230V - 2 wire

230V

0

w/ground

 

 

single phase

 

 

208V or 240V -

208V or

0

2 wire wground

240V

0

single phase

 

 

280V or 440V -

220V or

0

4 wire w/ground

254V

0

3 phase

 

 

380V - 3 wire

120V

0

w/ground 3

 

 

phase w/ stepdown trans- former

14. Disconnect the brewer from the power source.

If voltage is present as described, reinstall the level probe, the liquid level board and level probe are op- erating properly.

If voltage is not present as described, check the pink wire on the level probe from liquid level board terminal 4.

Removal and Replacement:

1.Remove all wires from the liquid level board.

2.Remove the #10-32 screw and flat washer securing the protective shield to the component bracket.

3.Remove the #10-32 screw and internal tooth lockwasher securing the liquid level board to the component bracket.

4.Remove liquid level board and discard.

5.Install new liquid level board on component bracket and secure with a #10-32 screw and internal tooth lockwasher.

6.Install protective shield and secure with #10-32 screw and flat washer.

7.Refer to Fig. 13 and reconnect the wires.

T1 BLU to Solenoid Valve

T2 BLK to ON/OFF Switch (All models except 230V-CE models)

T3 WHI to Main Harness (120/208V, 120/240V, four wire 380V and 440V models)

T3 WHI to Transformer

(380V three wire models)

T3 RED to Main Harness (208V, 240V single phase and three phase models) T3 BLK to Main Harness (230V two wire models)

T4 PIN to Level Probe

P1733

FIG.13 LIQUID LEVEL BOARD TERMINALS

Page 21

10060

080900

 

Page 21
Image 21
Bunn U3A service manual SERVICE cont, LIQUID LEVEL BOARD AND LEVEL PROBE cont