START-UP CHECKLIST

 

CUSTOMER:___________________________

JOB NAME: _______________________________________

MODEL NO.:___________________________

SERIAL NO.:____________________

DATE:_________

I.PRE-START-UP

DOES THE UNIT VOLTAGE CORRESPOND WITH THE SUPPLY VOLTAGE AVAILABLE? (Y/N)

HAVE THE POWER AND CONTROL WIRING CONNECTIONS BEEN MADE AND TERMINALS TIGHT? (Y/N)

HAVE WATER CONNECTIONS BEEN MADE AND IS FLUID AVAILABLE AT HEAT EXCHANGER? (Y/N)

HAS PUMP BEEN TURNED ON AND ARE ISOLATION VALVES OPEN? (Y/N)

HAS CONDENSATE CONNECTION BEEN MADE AND IS A TRAP INSTALLED? (Y/N) IS AN AIR FILTER INSTALLED? (Y/N)

II.START-UP

IS FAN OPERATING WHEN COMPRESSOR OPERATES? (Y/N)

IF 3-PHASE SCROLL COMPRESSOR IS PRESENT, VERIFY PROPER ROTATION PER INSTRUCTIONS. (Y/N)

UNIT VOLTAGE — COOLING OPERATION

PHASE AB VOLTS

PHASE BC VOLTS

 

 

PHASE CA VOLTS

 

 

(if 3 phase)

 

 

 

(if 3 phase)

PHASE AB AMPS

 

PHASE BC AMPS

 

 

 

PHASE CA AMPS

CONTROL VOLTAGE

(if 3 phase)

 

 

 

(if 3 phase)

 

 

 

 

 

 

 

IS CONTROL VOLTAGE ABOVE 21.6 VOLTS? (Y/N)

 

.

 

 

IF NOT, CHECK FOR PROPER TRANSFORMER CONNECTION.

TEMPERATURES

FILL IN THE ANALYSIS CHART ATTACHED.

COAXIAL HEAT

COOLING CYCLE:

 

F

FLUID OUT

 

F

 

PSI

 

FLOW

EXCHANGER

FLUID IN

 

 

 

 

 

HEATING CYCLE:

 

F

FLUID OUT

 

F

 

PSI

 

FLOW

 

FLUID IN

 

 

 

 

AIR COIL

COOLING CYCLE:

 

F

AIR OUT

 

F

 

 

 

 

 

AIR IN

 

 

 

 

 

 

 

HEATING CYCLE:

 

F

AIR OUT

 

F

 

 

 

 

 

AIR IN

 

 

 

 

 

 

CL-1

Page 23
Image 23
Carrier 50VS specifications START-UP Checklist, Ii. Start-Up