19th Century

CEILING HARDWARE

CROSSBAR

WIRE NUT (4)

MOUNTING

 

BRACKET

 

ADDITIONAL HARDWARE

21/4” x 8-32 ROUNDED HEAD SCREW (2)

1” x 8-32 ROUNDED

FLAT WASHER (2)

HEAD SCREW (2)

 

SUPPORT INSTALLATION PARTS

LAG SCREW

 

LARGE

 

FLAT WASHER

3/8” #7 X 5” (1)

 

 

3/8” (1)

CROSSBAR MOUNTING BRACKET INSTALLATION

Note: After removing the old fixture, check the outlet box to insure that it is supported by a joist or beam across its upper surface. If not, a 2” x 4” stud must be installed.

Step 1. Remove the knockout plug in the center of the outlet box or drill a 1/2hole for the lag screw to pass through. Then drill a 1/4guide hole into the joist or beam to a depth of 3.

Step 2. Route the outlet box wires through the keyhole slot of the crossbar mounting bracket as shown. Attach the crossbar mounting bracket to outlet box with screws provided, assuring that the outlet box wires are not pinched by the washer.

CAUTION: To reduce the risk of personal injury, use only the mounting hardware provided with the approved outlet box to install the crossbar mounting bracket.

WARNING!

SUPPORT DIRECTLY TO

BUILDING STRUCTURE ONLY.

JOIST

CEILING FAN

 

APPROVED

CEILING

WIRING BOX

WIRING

CROSSBAR

RIDGE

MOUNTING

SIDE

BRACKET

DOWN

GREEN GROUND

FLAT WIRE WASHER

APPROVED

OUTLET BOX

HARDWARE

5

Page 5
Image 5
Casablanca Fan Company PN9943001 Ceiling Hardware, Support Installation Parts, Crossbar Mounting Bracket Installation