4.0 EasiCheck Commissioning Request Form
Project Title: ________________________________________
Prior to the commissioning being undertaken, it is necessary that the contractor completes the
following information so as to aid system commissioning.
With reference to the above project we confirm;
Dedicated Mains Supply Installed Yes / No
All Fittings Installed Yes / No
All Fittings Addressed Correctly Yes / No
Schematics and Drawings Available Yes / No
Wiring Fault Free Yes / No
Loop +ve to Earth _______M-ve to Earth _______ M
Note: Typical readings should show infinity to Earth with a minimum of 1 M .
Please Schedule;
Installation/Address Inspection week commencing: ___ / ___ / ___
(1 weeks notice required)
System Commissioning week commencing: ___ / ___ / ___
(2 weeks notice required)
Reference should be made to the Project Plan Flowchart for timing of deliveries and
commissioning requests.
Upon receipt of this form, the confirmation requested for commissioning dates will be returned
to you. Failure to complete may delay system commissioning.
Signed on behalf of Contractor :
Above in Capitals :
Position :
Telephone Number :
Once completed, please return to;
Service Department
Cooper Lighting and Security Ltd
Wheatley Hall Road
Doncaster
South Yourkshire
DN2 4NB
TEL: 01302 321541
35
EASICHECK™