Cable Installation

Figure 14 Connecting Maintenance Bypass to GXT10000T-240X

 

 

 

 

 

 

 

 

 

 

120V

120V

 

TB2

NFINITY MAINTENANCE BYPASS CABINET WITHOUT

TB5

240V

 

 

L1

 

 

TRANSFORMER

 

 

 

1

 

 

 

L2

 

 

 

 

 

 

 

2

 

 

Input 2

N

 

 

 

 

 

 

 

3

 

 

 

 

 

 

 

 

 

 

 

 

 

G

 

Remove these three wires

 

 

 

4

 

 

 

 

 

 

 

 

 

 

 

TB1

 

for dual source

 

 

 

G

 

 

 

 

 

(see NOTE below)

 

 

 

 

 

 

 

L1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

L2

 

 

 

 

 

 

 

G

 

 

 

 

 

 

 

 

 

 

 

 

 

Input 1

N

 

TB3

 

 

 

TB4

 

G

 

 

 

 

 

 

 

 

 

 

 

G

L1

L2

G

1

2

3

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Flexible

 

 

 

 

 

 

 

 

 

Flexible

conduit

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

conduit

 

 

 

 

 

 

 

 

 

 

 

 

GEC

 

 

L1

L2

N

L1

L2

Input

 

 

Output

External Battery

GXT10000T-240X

 

 

 

NOTE

 

 

 

 

1. SINGLE-SOURCEFEED—If feeding the Maintenance Bypass Cabinet from a single source, the input connection may be made to either TB1 or TB2.

2.DUAL-SOURCEFEED—If feeding the Maintenance Bypass Cabinet from a dual source, the UPS input supply connection must be made to TB1 and the bypass input supply connection must be made to TB2. The jumpers between TB1 and TB2 must be removed.

21

Page 25
Image 25
Emerson GXT 10KVA user manual GXT10000T-240X