ENVISION CONSOLE INSTALLATION MANUAL

Unit Startup Checklist / Unit Startup Steps

Before Powering Unit, Check The Following:

High voltage is correct and matches nameplate.

Fuses, breakers and wire size correct.

Low voltage wiring complete.

Piping completed and water system cleaned and flushed.

Air is purged from closed loop system.

Isolation valves are open, water control valves or loop pumps wired.

Condensate line open and correctly pitched.

Transformer switched to 208V if applicable.

Dip switches are set correctly, if applicable.

Blower rotates freely

Air filter is clean and in position.

Service/access panels are in place.

Return air temperature is between 50-80ºF heating and 60-95ºF cooling.

Check air coil cleanliness to insure optimum performance. Clean as needed according to maintenance guidelines. To obtain maximum performance the air coil should be cleaned before startup. A 10-percent solution of dishwasher detergent and water is recommended for both sides of coil, a thorough water rinse should follow.

Startup Steps

Note: Complete the Equipment Start-Up/Commissioning Check Sheet during this procedure. Refer to thermostat operating instructions and complete the startup procedure.

1.Initiate a control signal to energize the blower motor. Check blower operation.

2.Initiate a control signal to place the unit in the cooling mode. Cooling setpoint must be set below room temperature.

3.Be sure that the compressor and water control valve or loop pump(s) are activated.

4.Verify that the water flow rate is correct by measuring the pressure drop through the heat exchanger using the P/T plugs and comparing to unit capacity data in specification catalog.

5.Check the temperature of both the supply and discharge water (Refer to Unit Operating Parameters tables).

6.Check for an air temperature drop of 15°F to 25°F across the air coil, depending on the fan speed and entering water temperature.

7.Adjust the cooling setpoint above the room temperature and verify that the compressor and water valve or loop pumps deactivate.

8.Initiate a control signal to place the unit in the heating mode. Heating set point must be set above room temperature.

9.Check the temperature of both the supply and discharge water (Refer to Unit Operating Parameters tables).

10.Check for an air temperature rise of 20°F to 35°F across the air coil, depending on the fan speed and entering water temperature.

11.Adjust the heating setpoint below room temperature and verify that the compressor and water valve or loop pump deactivate.

12.During all testing, check for excessive vibration, noise or water leaks. Correct or repair as required.

13.Set system to desired normal operating mode and set temperature to maintain desired comfort level.

14.Instruct the owner/operator in the proper operation of the thermostat and system maintenance.

Note: Be certain to fill out and forward all warranty registration papers.

41

Page 42
Image 42
Envision Peripherals IM1609 08 Unit Startup Checklist / Unit Startup Steps, Before Powering Unit, Check The Following

IM1609 10, IM1609 08 specifications

Envision Peripherals has carved a niche in the realm of advanced display technology, and its IM1609 10 and IM1609 08 models are no exception. These cutting-edge monitors are designed to meet a wide array of professional needs while delivering outstanding performance and visual clarity.

One of the standout features of the IM1609 10 is its impressive 16:9 aspect ratio and full HD resolution. This setup ensures that users receive crisp and vibrant visuals, whether they're working on intricate designs, analyzing data, or enjoying multimedia content. The IM1609 08 shares similar visual capabilities, making both models ideal for professionals in graphic design, video editing, and other visually intensive fields.

Both displays incorporate advanced LED backlight technology, which not only enhances color accuracy but also contributes to energy efficiency. Users can expect deeper blacks and brighter whites, resulting in a more dynamic visual experience. Furthermore, the IM1609 series features wide viewing angles, allowing multiple users to view the screen simultaneously without loss of quality or color distortion.

In terms of connectivity, the IM1609 10 and IM1609 08 come equipped with a range of ports, including HDMI, DisplayPort, and USB-C. This versatility ensures seamless integration with various devices, from laptops and desktops to media players and more. The USB-C port also allows for quick data transfer and charging options, catering to the needs of modern tech users.

Ergonomics is another key characteristic of the IM1609 series. With adjustable stands that allow for height, tilt, and swivel adjustments, users can customize their viewing experience for maximum comfort, reducing neck and eye strain during long working hours.

Additionally, the IM1609 monitors feature built-in blue light filters and flicker-free technology, which help to create a healthier viewing environment by minimizing eye fatigue. This consideration for user well-being is increasingly important in today’s tech-driven world, especially for professionals who spend significant time in front of screens.

Overall, Envision Peripherals’ IM1609 10 and IM1609 08 models represent the company’s commitment to blending performance, usability, and comfort into one seamless package. Whether for professional or personal use, these monitors deliver exceptional quality, making them a noteworthy addition to any workspace.