CHAPTER 1 Installation Planning Overview
Regarding the required staff in the installation planning group, consider the following:
zAn installation planning group and a supervisor within the user organization
zAn installation consultant from a Fujitsu or agent
1.3 Preparing Building and Facilities
Review the building and facilities needed to install a server system, ancillary
furnishings accompanying the server system, and the rooms needed to run the server
system.

1.3.1 Building and facilities needed to install a server system

Regarding the building and facilities needed to install a server system, consider the
following:
zBuilding
zPower supplies
zAir conditioning
zSignal line, telecommunication facilities
zFire extinguishers, fire extinguishing facilities

1.3.2 Furnishings accompanying a server system

Review the following furnishings accompanying in use of a server system:
zCabinets and lockers
- Small equipment
- Storage media
- Supplies
- Spare parts and maintenance tools
- Instructions manuals
zWarehouses
- Storage media
zTrucks