Step 5. Once the latching connectors are aligned properly and the mounting holes are aligned with stand offs then press slowly and firmly with two fingers (as shown below in Fig. 3.5.2f) on the top of the latching connectors until the connectors latched up securely.

Figure 3.5.2f: Securely latching up 6KPM Cards into a Magnum 6K25e

NOTE: All 6KPM slots need not be filled in order for the Magnum 6K25e unit to be operational. When leaving 6KPM slots empty, always use a face plate (Magnum 6K8- BLNK) to cover the slot opening in the front panel. This will maintain proper cooling air flow, safety, and operation as required by FCC, CE, and other regulations.

Step 6. Now screw down the daughter board with 6 #440 screws, so that it holds the daughter board securely. The figure below shows the top view of 6KPM card after successfully installing the 6KPM cards inside the Magnum 6K25e.

Fig. 3.5.2g Top View : 6KPM Module installed inside a

6K25e

Step 7. Once the installation of granddaughter and daughter modules is done, the front panel screen plates need to be placed on the front of the chassis cover to complete the installation process for that port module. The front panel screen plate comes along with the package of port module separately along with