FUNCTION TESTS
Test the Pothole Guards
Note: The pothole guards should automatically deploy when the platform is raised. The pothole guards activate two limit switches which control the machine drive speed. If the pothole guards do not deploy and the platform is raised above 1.8 m, an alarm sounds and the machine will not drive.
39 Raise the platform.
Result: When the platform is raised 1.2 m from the ground, the pothole guards should deploy.
40Press on the pothole guards on one side, and then the other.
Result: The pothole guards should not move.
41 Lower the platform.
Result: The pothole guards should return to the stowed position.
42Place a 2x4 or similar piece of wood under a pothole guard. Raise the platform.
Result: Before the platform is raised 2.1 m from the ground, an alarm should sound and the drive function should not work.
43 Lower the platform and remove the 2x4.
20 | Genie | Part No. 82784 |