3)The transfer switch will automatically monitor if the generator has sufficient available capacity to operate any or all appliances connected to PowerPause™ Load Management modules, starting with priority 1 Load, based upon appliance power requirements “learned” from a setup utility at the time of the transfer switch installation. One or more PowerPause™ Load Management connected appliances may operate simultaneously as long as the generator capacity utilization does not exceed 85%. If connected load exceeds 85% of generator capacity, the OVATION™ ATS will begin power management, and will lock out those appliances connected to the PowerPause™ Load Management modules in reverse priority order until the connected load is less than 85%. Those appliances that are “locked out” by the transfer switch will stay “locked out” for 5 minutes before the transfer switch will attempt to
4)During the utility power failure, the generator will continue to power the load until it either runs out of fuel (gasoline, propane or
5)When the utility power has been restored, the generator will continue to power loads for 60 seconds to ensure utility power has stabilized, then
6)The generator will continue to run without load for five minutes to cool down, and then is automatically shut off.
1.5 Key Components:
Model ATS1001D/R**
Ground Bar
Utility Main 100 Amp (See 1.5.2)
|
| Neutral Bar |
|
| [Branch | |
|
|
|
|
| Circuit | |
|
|
|
| |||
|
|
|
|
| Breaker | |
|
|
|
|
| Spaces] | |
| Control Module | |||||
|
|
|
| |||
|
| (Stabs onto |
|
|
| |
To Set Generator Size |
|
|
| |||
|
|
| ||||
To Set Exercise Schedule |
|
|
|
Current
Transformers*
(CT1 + CT2)
Drive Motor Assembly
Actuator (See 1.5.3)
Generator Main 100 Amp (See 1.5.2)
Neutral Bar
User Interface Display (See 1.5.1)
*Supplied with optional PowerPause™ Load Management Module (Model LSM)
**Not shown: ATSRK Relay Kit