Connect Solenoid Kit
A solenoid kit is required for some applicators used with Graco Metering Systems. See Individual Hoses on page 5 to see which applicators require a solenoid kit.
NOTE: To ensure proper operation of valve, install the solenoid kit within 15 ft (4.5 m) of the applicator. The solenoid reaction time decreases if the solenoid kit is farther away from the applicator. Ensure that the scuff guard covers the solenoid if mounted between the hose and whip hose.
1.Turn off all power to the system.
2.Apply anaerobic pipe sealant to pipe threads on mufflers (205), tee fitting (202), and swivel fitting
(215). Connect to valve (201).
3.Connect elbow fittings (204), and wire harness
(206)to valve (201).
4.Connect air hose (C) to swivel fitting (215).
5.Connect two elbows (207) and tubing (212) to open and closed ports on the applicator. See applicator manual for port locations.
NOTE: Cut tubing (212) to desired length if neces- sary.
206
207
205
212
202
204
215 205
201
r_24D161_3a0237b_1b
C
FIG. 14
Installation
6.Install plug (203), or tube fitting (214) and ball valve (213) in the other side of the tee fitting (202).
213202
207 212 214
203 r_24D161_3a0237B_2b
FIG. 15
7.For solenoid kit 24D161: Connect elbow fitting (207) and tubing (212) to the purge air port and tube fitting (214). See applicator manual for port locations.
Connect Splitter
24D160 and 24D161 use a splitter (211) to allow the Graco Metering System to dispense material from the system controls.
1.Connect the splitter (211) to the valve (201) with screw (208), washer (209), and nut (210).
2.Connect the hose communications cable (24) to the single splitter (211) connection.
3.Connect the wire harness (206) and signal cable (3b) from the whip hose to the splitter (211).
206 3b
208 210
209
201 211
24
r_24D160_3a0237b_1b
FIG. 16
3A0237L | 21 |