Installation continued
2. Burner/Blower Section
Use a crane and a spreader bar hooked to the factory lifting lugs (shown below) to lift and center the unit onto the filter stand section. The sections can be caulked together, but it is not needed with the water kickouts provided with this section.
3. Install Ductwork
This table shows the duct sizes and straight lengths recommended for optimal performance (AMCA Publication
Recommended Supply Ductwork Sizes
VSU | Duct | Straight Duct |
Blower Size | Size | Length |
|
|
|
220 | 68 x 26 inches | 117 inches |
|
|
|
4. Complete Installation
A typical horizontal discharge installation is shown. Gas and/or electrical lines can be connected at this time.
For upblast units, a duct elbow may be needed to turn the ductwork into the building. Follow proper ductwork methods recommended by AMCA to make this elbow to minimize duct losses.
4Model VSU
®