For Vertical Runs - The flue system must be
supported every 2.4 m above the heater flue outlet by
wall brackets.
To install support brackets for vertical runs:
Attach wall brackets to the flue pipe and secure the
wall bracket to the framing members with nails or
screws.
Figure 29. Installing Support Brackets
WALL BRACKET
WALL STUD
8 FT.
(2.4 m)
FLUE
OUTLET
1 INCH MIN.
(25 mm)
4. Install Firestops
For Horizontal Runs - Firestops are REQUIRED on
both sides of a combustible wall through which the
flue passes.
To install firestops (heat shield) for horizontal runs that
pass through either interior or exterior walls:
Cut a 10-inch by 12-inch (254 mm X 305 mm) hole
through the wall.
Position the firestops on both sides of the hole pre-
viously cut and secure the firestops with nails or
screws.
The pipe opening of the firestops MUST BE placed
towards the bottom of the firestop.
Continue the flue run through the firestop.