3-9. Installing Gas Supply
. DO NOT use Argon/Mixed gas regulator/flowmeter with CO2 shielding gas. See Parts List for optional CO2 gas regulator/flow- meter.
1
4
2
3
5 7
Argon Gas Or
Mixed Gas
6
Rear Panel
Tools Needed:
Obtain gas cylinder and chain to running gear, wall, or other stationary support so cylinder cannot fall and break off valve.
1Cap
2Cylinder Valve
Remove cap, stand to side of valve, and open valve slightly. Gas flow blows dust and dirt from valve. Close valve.
3Cylinder
4Regulator/Flowmeter Install so face is vertical.
5Regulator/Flowmeter Gas Hose Connection
6Welding Power Source Gas Hose Connection
Connect customer supplied gas hose between regulator/flowmeter gas hose connection, and fitting on rear of welding power source.
7 Flow Adjust
Typical flow rate is 20 cfh (cubic feet per hour). Check wire manufacturer’s recommended flow rate.
Ref. 220