Delivery space requirements
Be sure your facility has adequate space to receive and remove the
•Forklifts must enter and transport the shipping pallet from the side.
•Delivery plans must include the possible removal of walls or doors.
Dimension requirements | MCS expansion rack | |
|
|
|
Total length allowed to safely remove the | approximately 6.1 m (20 | approximately 6.2 m |
from the shipping pallet down the provided ramps | ft) | (20.6 ft) |
Packaged dimensions of the | 2285 mm (90 inches) | 2159 mm (85 inches) |
shock pallet and cartons) | height x 1219 mm (48 | height x 914.4 mm (36 |
| inches) width x 1829 mm | inches) width x 1727 mm |
| (72 inches) depth | (68 inches) depth |
|
|
|
Maneuvering space requirements
WARNING: To reduce the risk of personal injury or damage to the equipment, do not attempt to move equipment racks alone. Obtain adequate assistance to stabilize the rack during movement, or hire professional equipment riggers.
WARNING: To reduce the risk of personal injury or damage to the equipment, use extreme care when moving racks with casters. Sudden stops, excessive force, and uneven surfaces can cause the product to overturn.
When maneuvering the
•Move racks that have casters with care. Sudden stops, excessive force, and uneven surfaces might cause the product to overturn.
•Due to stability and safety concerns, the cooling unit and IT rack have casters that are fixed to the front and swivel in the back. For more ease, move the
•For long and straight distances, roll the
•When rolling the
•Be sure that the rooms and doors are large enough to accommodate the movement of the
•When transporting the
•When transporting the
The following figure shows the maneuvering space required when unloading the
Facility planning for implementation 21