Switch environment (MAP 0600)

Step 0600-007

You are here for one of the following reasons:

vAn over temperature condition exists

vYou fixed an obvious airflow blockage or removed a high temperature source near the air intakes

vA problem with the switch supervisor card sensors may exist

For any of the reasons listed above:

1.Perform ªSP Switch2 supervisor self-testº on page 3-6.

2.Does the card pass self-test?

v If yes, go to ªStep 0600-008º.

vIf no, replace the switch supervisor card. If the problem persists, call the next level of support.

Step 0600-008

The switch supervisor card passed the self-test.

1.Check the yellow switch supervisor LED for ON or FLASHING condition.

2.Is the yellow switch supervisor LED ON or FLASHING?

v If the switch supervisor LED is ON or FLASHING, return to ªStep 0600-003º on page 1-9 to determine if any other conditions exist. If no obvious problems are found, call next level of support.

vIf the switch supervisor LED is not ON or FLASHING:

a.You have resolved the problem.

b.Go to ªStep 0620-021º on page 1-27 to verify fix.

Step 0600-009

You found an obvious airflow blockage or abnormally high temperature source near air intakes.

1.Remove blockage or high temperature source.

2.Return to ªStep 0600-007ºto verify fix.

Step 0600-010

Perspective display shows ″PS X: Failure″ on a red background.

1.Use Table 1-5to service components

2.Refer to Chapter 4, ªFRU removals and replacementsº on page 4-1 for instructions about the component being serviced.

Table 1-5. Power supply failure diagnostics

Priority

Component

Action

 

 

 

 

1

Power Supply 1, 2, 3, or 4

a. Replace the power supplies.

 

 

(1 of 4)

 

b.

Continue at ªStep 0600-011º.

 

 

 

 

 

 

 

2

Switch supervisor card

a.

Replace the card.

 

 

(2 of 4)

 

b.

Continue at ªStep 0600-011º.

 

 

 

 

 

 

 

3

Switch planar

a.

Replace planar/chassis

 

 

(3 of 4)

 

b.

Continue at ªStep 0600-011º.

 

 

 

 

 

 

4

All replaced

Call next level of support.

(4 of 4)

 

 

 

 

 

 

 

Step 0600-011

You performed the recommended action in Table 1-5.

1.Component replaced or reseated.

2.Check the yellow switch supervisor LED for an On or flashing condition.

1-12RS/6000 SP: SP Switch2 Service Guide

Page 30
Image 30
IBM RS/6000 SP manual Power supply failure diagnostics

RS/6000 SP specifications

The IBM RS/6000 SP (Scalable Power) is a high-performance computing system that was developed in the early 1990s and has since become a significant player in the realm of supercomputing and enterprise solutions. Designed primarily for scientific, engineering, and complex data analysis tasks, the RS/6000 SP provides powerful processing capabilities, enhanced scalability, and features to support demanding applications.

One of the key characteristics of the RS/6000 SP is its modular architecture, which allows for the addition of multiple nodes. Each node is based on IBM's Power architecture, leveraging the RISC (Reduced Instruction Set Computing) design to achieve high throughput and efficiency. The system can support configurations ranging from a few nodes to hundreds, enabling organizations to scale their computational power as needed based on workload requirements.

The RS/6000 SP employs advanced interconnect technologies, most notably the SP Switch, which ensures high-speed communication between nodes. This interconnect allows for seamless data transfer, ensuring that the system can handle large datasets and complex computations without bottlenecks. The SP's ability to deliver concurrent processing capabilities makes it ideal for parallel computing tasks, including simulations, modeling, and large-scale computations.

In terms of software, the RS/6000 SP was equipped with AIX, IBM's version of the UNIX operating system, which provides a stable and secure environment for enterprise applications. Furthermore, the system supports a vast array of programming languages and tools, including Fortran, C, and C++, along with libraries and frameworks designed for high-performance computing. This compatibility allows developers to optimize their applications to fully utilize the underlying hardware.

Another notable feature of the RS/6000 SP is its extensive support for various workloads, including database management, multi-user applications, and graphical processing. The system was equipped with high-performance graphics capabilities, making it suitable for tasks that require intensive visualization, such as computer-aided design (CAD) and scientific visualization.

Overall, the IBM RS/6000 SP has solidified its role in the high-performance computing landscape, combining advanced technologies, robust scalability, and flexibility to meet the unique demands of research and enterprise environments. Its legacy continues to influence modern computing architectures, embodying IBM’s commitment to innovation and performance in the pursuit of complex problem-solving capabilities.