WALL MOUNT INSTALLATION – TOP VENT

***This installation only applied with the purchase of a duct cover (Model No. CH1120DC).

Preparation before Installation

NOTE: TO AVOID DAMAGE TO YOUR HOOD, PREVENT DEBRIS FROM ENTERING THE VENT OPENING.

-Decide the location of the venting pipe from the hood to the outside. Refer to Figure 13.

-A straight, short venting run will allow the hood to perform more efficiently.

-Try to avoid as many transitions, elbows, and long run as possible. This may reduce the performance of the hood.

-Use duct tape to seal the joints between pipe sections.

-If necessary, prepare back wall frame with cross framing lumber for secure installation.

-Using references on Table 2 and measurements on page 22-23, decide the level of the lumber. Refer to Figure 14.

Hood Preparation before Installation

-Temporarily wire the hood to test for proper operation before installing.

-Peel protective film off the hood and the duct cover (if any).

-Cut the multi vent exhaust according to the size of the venting pipe. Refer to Figure 15.

Figure 13

Figure 14

 

Figure 15

6" Round Vent

7" Round Vent

3-1/4"x 10" Vent

 

 

 