| INSTALLATION | ||
|
|
|
|
FIELD INSTALLED OPTIONS |
|
|
For installation of compatible field installed options (see the ACCESSORIES section of this manual and refer to the instructions included with those options.
REQUIRED EQUIPMENT-CONTROL CABLE CONNECTIONS
Follow the instructions below which are appropriate for the wire feeder that will be used.
LF-72 to CV-305
a)Turn the
b)Connect the
c)See OUTPUT CONNECTIONS for connection of work and electrode cables.
LN-7 to CV-305
a)Turn the
b)Connect the
c)See OUTPUT CONNECTIONS for connection of work and electrode cables.
LN-25 to CV-305
a)Turn the
b)Plug a K484 jumper plug into the
c)See OUTPUT CONNECTIONS for connection of work and electrode cables.
WARNING
The output terminals are energized at all times when the K484 is plugged in.
a)Turn the
b)Connect the
c)See OUTPUT CONNECTIONS for connection of work and electrode cables.
Connection of Remote Control (K857)
NOTE: The K864 Remote Control Adapter is required to install the K857.
Plug the K864 Remote Control Adapter into the power source's
OUTPUT CONNECTIONS
Output cables must have Magnum
Use the shortest possible cable lengths. See Table A.1 for recommended cable sizes based on length.
Connect the positive output lead to the terminal marked "+". The negative output lead can be hooked to either the low inductance terminal (marked " ") or the high inductance terminal
(marked " ").
TABLE A.1
Cable Sizes for Combined Lengths of Copper
Electrode and Work Cable
| Lengths up to |
|
|
Machine Size | 150 ft | 150 to 200 ft |
|
|
|
| |
|
|
|
|
315 A 100% | 2/0 (70mm2) | 3/0 (95mm2) |
|
|
|
|
|